Section 3. Linking Project Design, Annual Planning and M&E
HOME
Introduction
M&E and Impact
Design, Planning and M&E
System Set-up
What to Monitor
Information Management
Capacities and Conditions
Critical Reflection
Glossary
Logframe Sample
M&E Matrix Sample
M&E Methods
Sample TORs


 

 

 

 

 

3.1 An Overview of Linking Project Design, Annual Planning and M&E

When you "manage for impact", project design, annual planning and M&E become linked processes. Your starting point for implementation is the initial project design as outlined in the project appraisal report. But design is an ongoing process for the life of the project. Continually adapting the project strategy in response to new understanding and to changing contexts is key in maximising impact on rural poverty. So, good project design is as important for managers and M&E staff as for the initial design team.

Key aspects of a project’s design are built into the project loan agreement. Changing these can be difficult and time consuming. Thus it is critical that the initial design be as high quality as possible. In addition, the initial design team must build in flexibility to allow changes at project start-up when the design is revised. The PROCHALATE project in El Salvador learned the importance of rethinking the design the hard way. Staff there estimate that they could have prevented the loss of two years at the beginning if implementers had had better understanding.

3.1.1 Project Design as an Ongoing Process

Why is change to the project design necessary? First, many projects start up to several years after initial design, during which the context will have changed. The project cycle (see Section 1.4) includes the many steps that lead to start-up, each of which takes time. Second, the initial design of IFAD-supported projects is undertaken with limited time and resources. Many of the implementing partners will not have been identified and so there will have been limited participation in the process. This means that a comprehensive participatory process of reviewing and, where necessary, improving project design is critical at start-up. After start-up, the two main opportunities for improving the project design are: (1) on an annual basis as part of the annual progress review and planning process and (2) during the mid-term review (MTR). Table 3-1 lists the design and adaptation tasks during the project’s lifetime, showing how (re-) design is ongoing.

Table 3-1. Design and adaptation tasks at key moments during the project lifetime

Moment in Project Life

Design Tasks

Initial design phase

- Assess feasibility, scope and rationale of project.
- Determine the goal and objectives.
- Outline main project outputs and key activities.
- Outline project implementation process and structures.
- Outline the M&E system.
- Develop the budget and specify staffing levels.

Start-up phase

- Develop understanding of project goals and objectives with key stakeholders.
- Review and revise the initial design.
- Design and plan work in sufficient detail to allow for implementation.
- Develop a detailed operational M&E system.

Annual review of the work plan and budget

- Check if the outputs, purpose-level objectives and goal remain relevant; adjust.
- Decide what activities and tasks are necessary to deliver outputs.

Supervision (recurrent)

- Discuss overall progress of the project.
- Decide on changes that should be made in the annual work plan.
- Assess any potential changes in the overall design that require loan agreement negotiations.

End of the early implementation phase

- Review overall project strategy in light of early implementation experience.
- Develop recommendations for the work plan in the next phase.
- Negotiate any significant changes to project design for the next phase.

Mid-term review (or reviews between phases if the project has a flexible lending mechanism)

- Review achievement of outputs and progress towards the purpose(s) and goal.
- Assess appropriateness of the overall strategy.
- Redesign the project as necessary.

Beginning of the phase-out period

- Identify the priorities of final activities in order to maximise impact.
- Review and adjust strategies with a view to sustained impact.

3.1.2 Good Practices for Project Design

There are six good practices in any design process of a development intervention. They are critical during formulation and start-up and when any revision of the project is undertaken, such as during annual and mid-term reviews.

1. Involve all relevant stakeholders in participatory processes of project design.
2. Undertake a thorough situation analysis, together with primary stakeholders, to learn as much as possible about the project context as a basis for designing a project strategy and implementation processes that are relevant.
3. Develop a logical and feasible project strategy that clearly expresses what will be achieved (goal and purposes) and how it will be achieved (outputs and activities).
4. Agree and fous on cross-cutting issues of poverty, gender and participation.
5. Plan for long-term capacity development and sustainability to ensure that the project contributes to the empowerment and self-reliance of local people and institutions.
6. Build in opportunities and activities that support learning and enable adaptation of the project strategy during implementation.

3.1.3 Using the Logical Framework Approach

Since 1998, IFAD has required that projects be designed using the Logical Framework Approach (LFA). This process was originally developed in the 1970s to improve the quality and clarity of project design. The LFA process is based on participation of key stakeholders, including primary stakeholders. The project design that results from the LFA process is summarised in a table that is referred to as the logical framework matrix, or logframe (see Section 3.3.2). While the LFA has become widely accepted as useful for project planning, it also has some clearly recognised problems. So the standard LFA planning process has been improved in different ways over the years. Flexible and critical use of the LFA means:

  • recognising that development is not mechanical by building options and opportunities for adaptation into the design;
  • valuing outcomes (achievements between tangible outputs and long-term impacts) by making them explicit in the logframe;
  • avoiding over-simplification of large projects or programmes by using multiple purposes, a cascading logframe or a five-layer logframe;
  • including people’s visions and aspirations and identifying opportunities during the planning rather than focusing only on problem analysis;
  • recognising that quantifiable indicators and qualitative information, such as opinions and stories of change, are needed for M&E;
  • guarding against bureaucratic control by reporting more on outcomes, (interim) impacts and planned improvements – and less on activities and outputs;
  • avoiding token use of the logframe matrix by ensuring it represents the shared vision for the development intervention, by using it as a management tool and by keeping it updated;
  • tracking assumptions as part of M&E to help guide the project strategy.

Note that a project can be designed well in different ways – and that the LFA is only one of these ways. Also, using the LFA is certainly no guarantee of ending up with a good project design. You need to be both critical and creative to achieve a design process that is appropriate for the context.

3.1.4 Linking Project Design with the Annual Work Plan and Budget

The project logframe will show the main activities for the life of the project. Each year the implementers need to identify which activities are needed for the coming year and prepare a budget. The logframe is the basis for the annual work plan and budget (AWPB). For the logframe to be useful, it must be sufficiently detailed and, in particular, updated to reflect the current situation of the project. For example, the original logframe may have included outputs or even components that are no longer appropriate and have been dropped. How the project appraisal report is translated into operational plans varies enormously across projects, although all have annual plans. Some have an overall operational plan with milestones that look at key implementation over the project’s lifetime, which can help translate the logframe into annual clusters of activity. Others have "project implementation manuals" that detail operations. Some have two- or three-year operational plans, alongside annual plans.

3.1.5 Linking M&E to Project Design

Developing M&E starts long before start-up. Initial project design strongly influences the ease with which M&E is implemented later on through, for example:

  • the relationships and commitment established with partners and local people, particularly the intended primary stakeholders;

  • the logic and feasibility of the project strategy;

  • the resources allocated to M&E (funding, time, expertise);

  • the degree of inbuilt flexibility that allows M&E findings to have a steering function;

  • any operational details of M&E that might be established during initial design.

During project formulation, a broad M&E framework should be developed and included in the formulation and appraisal documents. This framework provides: a) sufficient detail to enable budgeting and allocation of technical expertise, b) an overview of how M&E will be undertaken, and c) some guidance for project staff about how M&E should be set up during start-up. The M&E framework complements the highly summarised M&E information that is the logframe (see Section 3.4). Much of what is developed for the M&E system during the initial project design phase will only be indicative of the final plan and will need to be revised and refined during start-up.

Back to Top

3.2 Designing for Learning, Empowerment and Sustainability

Designing a good rural development project requires careful attention to the social processes and institutional development that will enable learning and the empowerment of primary stakeholders and lead to sustained benefits.

3.2.1 Involve Stakeholders in Project Design Processes

Projects without good stakeholder consultation are setting themselves up for failure. Those that do consult widely increase their chances of success. Box 3-1 describes a simple case in Ghana where a participatory process created the opportunity for primary stakeholders to adjust part of the strategy to make it appropriate to their situation and thus more likely to meet their real needs. Involving stakeholders in project design is important specifically for:

  • inspiring them to identify, manage and control their own development aspirations, and so empower themselves;
  • ensuring the project goals and objectives will be relevant and, as a result, meet the real needs of the rural poor;
  • ensuring the project strategy is appropriate to local circumstances;
  • building the partnerships, ownership and commitment needed for effective implementation.

Local participation early on can also be cost-effective in the long run. In Uganda, more time and money were spent to involve primary stakeholders in a more inclusive formulation process of the District Development Pilot Project, which was then found to be effective because of local inputs and ownership and a deeper understanding of the project. If the investment hadn’t been made up front, much money would have to have been spent later for one-way information campaigns before and during project implementation.

 

Box 3-1. Community participation in the project design process

When the irrigation specialist of Zebilla District, Ghana, shared his plans for the rehabilitation of the earthen dam and irrigation network in the village of Saka, the village water users’ association (WUA) quickly sent him back to the drawing board! Many years before, when the dam was first constructed and functioning, the village had established a substantial mango orchard directly below it. Even though the dam had not been working for the past 17 years, the mangoes had continued to produce each year. With the start of the IFAD-supported LACOSREP project, the villagers had formed self-help groups, elected a WUA and requested their dam to be rehabilitated under the project. The project’s irrigation specialist then recommended cutting down most of the mango trees to make room for an expanded irrigation scheme just below the dam. The community objected, as the mangoes were valued, especially during the dry season. One older man explained, "With the mango trees, I know that my children will have something to eat during the lunch break at school." The villagers suggested extending the canal beyond the mango orchard instead. This way, not only would the orchard be saved, but the canal would expand the amount of cultivable, irrigated land.

 

The first step in project design is to conduct an initial stakeholder analysis (see Annex D for more detail). This requires listing potential stakeholders (individuals, social groups and organisations), prioritising who must be involved (and not everyone who it would be nice to involve) and agreeing with them on how they can best be involved. This is the basis for being able to understand their needs. Box 3-2 lists questions developed by a project in Tanzania to guide an analysis of stakeholder needs.

Box 3-2. List of questions to outline multi-stakeholder-level strategy for the PIDP project in Tanzania

Farm Household Level

* What is the present situation of the farm household?
* What does the future, improved situation of the farm households look like?
* What changes have to be undertaken at farm household level?
* What support do farm households need?
* What support do farmers and members of the water users’
association need?
* Who is to provide the support?

Water Users’ Association (WUA)

* What is the present situation of the WUA?
* What does the future, improved situation of the WUA look like?
* What changes have to be undertaken at the level of the WUA?
* What support do the WUAs need?
* Who is to provide the support?

District Councils (DCs)

* What is the present situation of the DCs?
* What does the future, improved situation of the DCs look like in terms of mandate, structure and services offered?
* What changes have to be undertaken at the level of the
DC and district-level project management unit?
* What support do DCs need?
* Who is to provide the support?

Programme Coordination Unit (PCU)

* What is the present situation of the PCU?
* What does the future, improved situation of the PCU look like?
* What changes have to be undertaken at the level of the PCU?
* What support does the PCU need?
* Who is to provide the support?

  Stakeholder participation in design is not limited to working with local communities or valuing their views above others. The idea of a "community" that one consults is quite simplistic and can cause problems. For example, if implementing partners or project staff consult a community, will all local voices be heard? Which ones will unintentionally be forgotten or ignored? Also, what is good for one community is not necessarily good for another or for its region. So which community will you listen to if they have differing opinions? Understanding differences within and between local communities means listening, listening and listening again – and working together. Only then can you gain insights into local relationships and interests. Some people think that illiteracy and geographic isolation of target groups makes participation impossible. But many examples show how including the poorest, most isolated and illiterate of groups is possible with some creativity and time (IFAD/AGNGOC/IIRR 2001 publication, see Further Reading). Good participatory processes involve sharing perspectives and negotiating differences. Stakeholders can be involved in many ways, including comprehensive participatory rural appraisal (PRA) processes, informal discussions and planning workshops. However, people’s physical presence is not enough. Some very poorly designed projects have included many local people who did not participate freely. Ensuring high-quality participation is key and will require creating project structures that can respond to people’s requests (see Box 3-3).

 

Box 3-3. New project structures in Colombia to create space for participation

The PADEMER project in Colombia negotiated several recommendations when refining the project at start-up: 1) changing focus from supply to demand, wherein project activities start with a participatory process of identifying rural microenterprise demand for services, 2) introducing competition through open tenders for service delivery, and 3) forming regional groups for selecting and prioritising projects, with primary stakeholder representatives invited to assist in selecting and supervising service delivery contracts.

 

Good project design requires questioning, sharing and negotiation. This happens when good information is available and when differing perspectives between community people, scientists, NGO staff and government officers are discussed openly and negotiated. Planning workshops with stakeholders are important, and a good process, understood by all, will help achieve a valuable outcome. Some projects focus on a single workshop. This creates pressures; and agreements may be made that do not make much sense afterwards. It might be tempting to think that, because such outputs came from the stakeholders during the workshop, they are "correct" and cannot be changed. However, people learn by participating in dialogue. The views they held in one meeting might change. The next day, after having had a chance to reflect and discuss with others at home, they might see things quite differently. So rather than a one-off workshop, it is better to hold a sequence of events where people’s ideas can be shared and merged, and informed agreement can be reached (see Box 3-4).

 

Box 3-4. A workshop process for participatory logframe design in Uganda

Ugandan project staff recommend the following workshop process for developing the logframe. At the beginning, they draw a diagram that shows the process in terms of steps to be undertaken through the workshop. This includes scanning the project environment, developing the vision, mission, goals and purposes (impacts) for the project, and then filling in the details of outputs and activities. By referring back to the visual diagram of the workshop process, participants can see the progress they are making in working through the LFA steps. The workshop lasts about two to three days. At the end, participants find they have worked through the whole logframe matrix themselves.

 

3.2.2 Be Clear about Cross-Cutting Issues: Poverty, Gender, Participation

A shared understanding by stakeholders of the concepts of poverty reduction, gender equity and participation is critical. It is the only way to secure agreement on how to build these concepts into the project strategy. Differing understandings can lead to diverging objectives. For example, in one project in Yemen, concerns were raised about the CACB’s (Cooperative Agricultural Credit Bank) apparent lack of commitment to the project target group of small farmers. Then project staff discovered that the CACB was defining as eligible all small farmers within the project region. However, the project was targeting only those from 47 specific villages involved in project shelterbelt activities, as named in the project design documents. Different definitions had caused frustration and disrupted monitoring of credit activities. Defining what these three concepts mean for the intended implementers is the first step. M&E experiences in India revealed that the intention to target the poorest of the poor was not always fulfilled because the official criteria for "below poverty line" (BPL) were inadequate for the project. An NGO there used the official criteria in "wealth ranking" and "wealth mapping" methods to check the proportion of village members from poor households against the status of households who had not joined the self-help groups (SHG). They found that many households not in the SHGs did not meet the BPL criteria, yet they were still living in relative poverty.

Agreeing on terms like "poverty" and "basic necessities" is essential both for good project design and M&E. Opportunities for reaching agreement need to be created. For example, the ADIP project in Bangladesh took a group-based extension approach and kept close ties with NGOs and local agencies in the project design. This created good opportunities for agreeing on poverty indicators that guide some M&E.

The same is true for "gender" and "participation" (see Section 2.7). Even when everyone agrees on these concepts at the onset, they need to return to them regularly to limit deviations from a goal in poverty reduction and equitable development. Nevertheless, differing opinions may remain, as the activities based on these definitions are implemented in the organisational context of each stakeholder group (see Box 3-5).

 

Box 3-5. Definitions in an organisational context

In one project area in North Africa, the president of a rural community, who also worked in local government, was involved in linking project staff and local people. He found it difficult to justify investing the limited project resources only in poor households. Instead, he tried to spread out project resources to as many people as possible, especially those who were motivated and capable of completing what the project had started. He explained, "For the land rehabilitation work, we have the resources to remove stones on one hectare of land per household, so we choose people with more than one hectare who will be able to remove the stones from the rest of their land with their own resources." People with more land and capacities were not the poorest, but the strategy was understandable. The local government, in which he worked, had the mandate to organise service delivery for the majority of citizens rather than to the project target of only the poorest.

 

3.2.3 Plan for Capacity Development and Sustainability

Many IFAD-supported projects focus on delivering infrastructure and public facilities– wells, roads, covered markets, clinics, school buildings, etc. But it is the people who use and maintain a structure. A major lesson learned by development agencies over the past 25 years is that investing in capacities is at least as important as in infrastructure for sustained poverty reduction. An interesting example of what this may mean in practice comes from the WUPAP programme in Nepal. Its overall purpose is "To assist in self-empowerment and in strengthening the capacity of poor and socially disadvantaged groups of people to: mobilise and increase their own resources; gain access to external resources; claim social justice." [Emphasis added.] To ensure this focus, questions to consider during project design and adaptation are:

1. Whose capacities are being built through the project?
2. Will these capacities reduce rural poverty?
3. If not, what else do we need to do in terms of capacity-building to have a lasting local impact?

Some people think that capacity development simply requires counting how many people attend training workshops. But attending a workshop does not necessarily strengthen capacity. Building capacity requires conscious effort to share decision-making with primary stakeholders over time (see Box 3-6).

 

Box 3-6. Participation and capacity-building for sustained impact

The Cuchumatanes project in Guatemala worked with organised farmers: formal organisations, interest groups and communal banks. In 1998, a primary stakeholder committee was created to strengthen their participation in project management. It supervised field activities and collected primary stakeholders’ claims. When the project finished in 2000, the primary stakeholder committee became an association called the Association of Organisations of the Cuchumatanes

 

Monitoring and evaluating capacity-building is not as straightforward as counting infrastructure changes. "Capacity" is sometimes difficult to describe clearly in ways that will allow measurable indicators and may therefore require additional creative thinking. Box 3-7 compares performance indicators for Nepal’s WUPAP rural infrastructure component with indicators from a similar component in a project in China. Note that including a capacity-development focus requires a participatory M&E approach – only the stakeholders themselves can explain if and how capacity might have been built. For example, capacity is not about how many kilometres of road have been built, but how stakeholders are going to ensure that these roads are maintained, used and extended.

Box 3-7. Comparing indicators that foster capacity development with ones neutral towards it (Note: the italicised words indicate where capacity development is made explicit.)

Project Output

Performance Indicators in the Project Logframes

WUPAP Nepal

Infrastructure programme implemented

- Rural infrastructure schemes identified, constructed and maintained by disadvantaged groups on a demand-driven basis

- Infrastructure-related policy developed and enforced that benefits the disadvantaged

  • Number of small-scale or micro irrigation schemes constructed/rehabilitated and maintained
  • Kilometres of trails and number of bridges constructed/rehabilitated/maintained
  • Number of community facilities (including storage facilities) constructed and maintained
  • Number of water supply and sanitation schemes constructed/rehabilitated and maintained
  • Number of disadvantaged groups successfully expanding irrigated area and the per cent by which the irrigated area increased
  • Kilometres of rural roads constructed/rehabilitated and maintained: 75
  • Per cent of labour for earthworks provided by the target group identified by the communities and social mobilisers: 70 (of which at least 50% are female)
  • Number of disadvantaged people employed through component
  • China project

    Rural infrastructure constructed or rehabilitated

    • Number of primary stakeholder households served by new domestic water supplies: 25,000
    • Kilometres of rural road network upgraded to class 4: 198
    • Number of villages supplied with electricity: 67
    • Number of household biogas systems installed: 22,500

    Including a capacity-development perspective has implications for policy, as existing policies can be questioned when local people take more charge of their own situation. By explicitly linking project activities to specific policies, the project team has the opportunity to engage and provide feedback to policy makers. The ADIP project in Bangladesh found this when it aimed to implement the government’s New Agricultural Extension Policy. In the process, the project created opportunities for informing government on the policy itself. This link has two advantages: providing primary stakeholders with a voice at policy level and ensuring that local capacity-building stays in tune with the current policy outlook. Good capacity-building is essential for sustained impact. Three points need particular consideration.

    1. A broad base. Capacity-building must include not only primary stakeholders but also other key stakeholders, particularly local government (see Box 3-8).
    2. The plan for phasing-out. Project managers in India have systematic phasing-out plans that list specific responsibilities to be able to show sustainable outcomes for their investments in local development.
    3. Sensitivity in M&E. Tracking and evaluating capacity development is particularly sensitive because it focuses on people and makes judgements about their activities.
     

    Box 3-8. From project focus to supporting local governance

    The terms of reference for M&E expertise in Uganda’s District Development Support Project (DDSP) focused only on the project. Staff recognised that this could easily be changed to become a local government M&E framework that benefits the district as a whole. For the consultant to contribute to the district, and not just the project, he/she should:

    • know and understand the local government system in Uganda;

    • work closely with the DDSP team to create a multi-level, multi-stakeholder M&E system for the planning, allocation and implementation needs of the local governments. This would include mentoring the district planning units and other departments to help their partners/other stakeholders develop their own indicators for the M&E of local government services;

    • work closely with the efforts of other agencies in developing M&E systems for local governments;

    • ensure that the roles and responsibilities fit within existing local government/authority roles and responsibilities (so as not to create unsustainable committees, organisations or positions);

    • have documentation and dissemination skills to assist local governments to develop communication strategies for meeting their constituencies’ learning and information needs; for example, assist by documenting the local government’s M&E framework for wider dissemination and use by other districts in Uganda.

    In this way, there can be a shift in focus from short-term project learning to the development of longer-term institutional change.

     

    3.2.4 Plan for Learning and Adaptation During Implementation

    Any project will require many adjustments during its life. This is guaranteed. Do not overly detail a project strategy, as this hinders adjustments during implementation. Here are some ideas for a design team to build learning opportunities and change into the design.

    • Design the process, as well as objectives, at the higher levels (also see next point). Identify the forums and processes that will be used to involve stakeholders in project review and adaptation, and build in flexibility to respond to unplanned opportunities. This approach was used to advantage by the TEPP project in Yemen to involve emerging stakeholder groups in information-gathering and feedback. Local communities had a strong sense of group action. When local youths saw what the project was beginning to develop, they started to participate voluntarily in certain aspects, lending a hand with seedling protection, community health and water supplies. The project was able to involve them in implementation and M&E, and so gained valuable support and informal feedback on the field situation.
    • Focus on clear goals (impacts) and purposes (outcomes), rather than over-specifying activities and outputs. Project design teams commonly over-specify activities and spend time on the overall goal, then they fill the in-between steps with hastily formulated purpose(s) or outcomes. Yet these interim levels are the most important part of "managing for impact" so require most of the attention. This approach can also have secondary benefits, as was seen in Ghana where the second phase of a project was designed to be less targeted and more flexible. Project management and the cooperating institution were given the authority to adjust the components and outputs in the design to respond to locally expressed targets. This more flexible design also increased the involvement and ownership of the project by the primary stakeholders.
    • Be explicit about uncertainty. Instead of trying to force specificity, explain what you simply do not yet know, such as exactly how communities will want to administer local development funds. Explain what is unknown and how and when project management should be clear on the issues. This means suggested targets should be approximate. State quantitative targets as being approximate and describe how the project could revise them, if necessary. For example, the logframe of the WUPAP programme in Nepal explicitly states: "As the programme is demand driven, the output targets remain highly indicative and in some cases are not specified in detail… The logframe should be regarded as indicative, as it will need to be reworked by its stakeholders in the course of implementation."
    • Build in mini-research phases at key moments. Not all issues of relevance to a project can be anticipated ahead of time. List as an activity and budget for "focused studies" to answer questions about the project context that may arise. For example, if the project is testing a new kind of micro-credit scheme, then before this is expanded a focused and detailed interim evaluation is needed.
    • Make it explicit that the project strategy and logframe matrix should be revised each year. Annual adjustments to the logframe are increasingly accepted and expected. A project design can indicate when and with whom this will take place.
    • Make "adaptive management" a key function in the terms of reference for senior management and partner contracts. When hiring managers and selecting partners, select those who can balance uncertainty with being clear about poverty reduction goals.
    • Budget for experimentation and for the unexpected. If the project is testing a new approach, then the budget should reflect this and more money should be allocated to later years when there is more certainty about expanding the approach. Also leave a portion of the budget and staff time for activities that do not fit into established categories. In some companies that must innovate to survive, researchers can spend 10% of their time on activities of their own choosing. This allows them to respond to unexpected opportunities.

    Back to Top

    3.3 Introducing the Logical Framework Approach

    The logical framework approach (LFA) can be very useful for guiding project design and implementation. The basic ideas behind the LFA are simple and common sense for any design process.

    1. Be as clear as possible about what you are trying to achieve and how it will be achieved.
    2. Decide how you will know if you are achieving your objectives and put in place a monitoring system.
    3. Make explicit the conditions (assumptions) outside the direct control of the project that are critical for the project to succeed and assess the risk for the project if these conditions fail to arise or change.

    The LFA also has some limitations. The main criticism is that it can lead to a rigid and bureaucratically controlled project design that becomes disconnected from field realities and changing situations. However, the LFA is easy to use more adaptively, particularly if the original design is seen, at least in part, as needing future finalization and probably revision, and project management prioritises annual reviews and logframe updating. The logframes of IFAD-supported projects vary widely in their quality, application and terminology. Design teams using the logframe for IFAD-supported projects commonly experience difficulties. These arise because IFAD-supported projects are long term, aim at high-level poverty reduction goals and aim to undertake a wide range of development activities. These features require a fine balance between too much detail and oversimplification. So in practice, a summarised logframe will be useful to provide an overview of the project and for those making decisions about project funding. For those using the logframe as a management tool, more detail will be needed. When facilitated well, the LFA is generally seen as very valuable by project stakeholders (see Box 3-9) and leads to a better quality and shared understanding of needs, objectives and strategies by all involved. When possible, try to follow the basic ideas without forcing everyone to understand the full detail of the logframe matrix. Visually mapping out the process steps can make them clearer than using the four-column table format. It may also be a good idea to avoid some official terminology, finding local words instead. Some people may be scared off by terms like "logframe" and "objectively verifiable indicators". These practices all lend to flexible use.

     

    Box 3-9 Usefulness of the logframe, as seen by primary stakeholders

    When members of the water users’ association of the PIDP project in Tanzania were asked their opinions on the logical framework approach, they gave the following comments:

    • "It makes planning easier."
    • "Now we have a plan for the year. It helps us in scheduling and priorities."
    • "With this kind of meeting [LFA process] we get time to sit together with the technical staff and the farmers to talk about our problems and the solutions to our problems. It is a teaching approach to solving problems."
    • "It was difficult to understand in the beginning. But then when you understand, it is easy for planning."
    • "Unlike the first projects [previous development projects], now we have indicators so that we are able to judge our achievements. The problems from the first project had been continually carried over until now."
     

    3.3.1 Key Steps in the Logical Framework Approach

    While most people are familiar with the logical framework matrix, the most important part of the LFA is actually the planning process that has been developed to improve the quality and clarity of project design. There are various versions of the steps in the LFA. The one presented below takes account of the specific nature of IFAD-supported rural development projects. The key steps to be undertaken – with well-selected and diverse stakeholders – are:

    1. establish the general scope or focus of the project;
    2. agree on the specific planning framework, terminology and design process;
    3. undertake a detailed situation analysis;
    4. develop the project strategy (objective hierarchy, implementation arrangements and resources);
    5. identify and analyse the assumptions and risks for the chosen strategies, modifying the project design if assumptions are incorrect or risks are too high;
    6. develop the monitoring and evaluation framework.

    Each step is discussed in more detail in the next sub-section, with detailed examples of the logframe matrix in Annex B and of the M&E matrix in Annex C.

    3.3.2 The Logical Framework Matrix

    The written output of the LFA is the logframe matrix. The standard matrix is a table with four rows and four columns. This matrix summarises:

    1. what the project should achieve, from the level of an overall goal down to specific activities;
    2. the performance questions and indicators that will be used to monitor progress and overall achievement;
    3. how these indicators will be monitored or where the data can be found;
    4. the assumptions behind the logic of how activities will eventually contribute to the goal, plus associated risks for the project if assumptions turn out to be incorrect.

    Table 3-2 shows a logical framework matrix appropriate for IFAD-supported projects and consistent with ideas in this Guide. Alternative, commonly found terms used in the matrix are given in parentheses. Note that inputs required for activities to be carried out are written at the activity level in the second column (Performance Questions and Indicators) – the column is not for indicators. The table also suggests how to write the objectives in the hierarchy.

    Table 3-2. The logical framework matrix and how each level is written (alternative common terms in parentheses)

    Objective Hierarchy

    (Narrative summary, intervention logic)

    Performance Questions and Indicators

    (Objectively verifiable indicators, indicators, targets)

    Monitoring Mechanisms

    (Means of verification, sources of information)

    Assumptions and Risks

    Goal
    (Overall objective, development objective)

    The long-term objective, change of state or improved situation towards which the project is making a contribution

    How to write it: put the verb in the past tense, as something already achieved over the long term

    Performance questions and Indicators at goal level – high-level impacts

    How necessary information will be gathered

    For long-term sustainability of the project

    Purpose

    (Project development objective)

    The immediate project objective, the overall observable changes in performance, behaviour or resource status that should occur as a result of the project

    How to write it: put the verb in the present or past tense as if already achieved

    Performance questions and indicators for each purpose (component) – lower-level impact and outcome indicators

    How necessary information will be gathered

    Assumptions in moving from purposes to goal

    Outputs
    (Results)

    The products, services or results that must be delivered by the project for the component objectives and purpose to be achieved

    How to write it: put the verb in the present or past, as if already achieved

    Performance questions and indicators for each output – output indicators

    How necessary information will be gathered

    Assumptions in moving from outputs to purposes

    Activities

    The actions taken by the project that are required for delivery of the outputs

    How to write it: put the verb in the infinitive, as something to do

    Note: the needed inputs go here, not indicators for activities

    Assumptions in moving from activities to outputs

    When using the logframe flexibly for IFAD-supported projects, two issues are important: (1) knowing how to use the matrix for large projects or programmes and (2) making sure outcomes are adequately considered.

    Using the Matrix for Large Projects or Programmes

    Many IFAD-supported projects involve diverse components, including health, infrastructure, extension support, irrigation development, micro-finance, organisational development and social justice. Each of these different elements could be considered projects in their own right, although they are often closely linked. So some IFAD "projects" are more like programmes, in the sense that they involve a diverse range of loosely-coordinated initiatives being implemented by different groups for the same overall goal. Three problems occur when large and multidimensional projects (or programmes) are summarized into a four-by-four logframe matrix.

    1. The project is oversimplified to such an extent that the matrix provides insufficient detail for effective management or M&E.
    2. Outcomes, outputs and activities tend to become confused. For example, what might be an overall outcome for the irrigation component is written in the matrix as an output of the project; then, what are really irrigation-related outputs are included in the matrix as project activities.
    3. Insufficient detail is given at the purpose level in defining the outcomes needed to guide the project strategy towards impact (see Section 2.3).

    You have three options for overcoming these problems (see Table 3-3).

    • Introduce multiple purposes for the project. With projects that have a number of components, each component then has a separate purpose. This is commonly done with IFAD-supported projects. (Be aware that some versions of the LFA only allow one purpose per project). Try to avoid viewing large project components as outputs. An output is a specific deliverable product or service, whereas a project component is broader and is achieved by the delivery of a series of outputs.
    • Use the idea of a "cascading logframe". View your project in terms of one master logframe matrix, with a series of smaller, linked logframes (or sub-projects).
    • Extra level of objectives. Introduce an extra layer into the logframe matrix between "Outputs" and "Purpose", which could be called "Component objectives" or "Key outcomes".1 Many projects already implicitly or explicitly work with this idea but do not include it in the logframe matrix.

    The most common version of the LFA suggests only one purpose per project. However, the size, range of components and long timeframe of IFAD-supported projects means that having a single project goal and only one project purpose is not helpful. Therefore, many IFAD-supported projects have moved to using multiple purposes that relate to each of the major components. It is this model of the logframe matrix that guides the examples in the Guide.

    Another problem of concern in complex projects is the difficulty of including cross-cutting concerns in a linear objective hierarchy. For example, you may want to pay particular attention to women’s empowerment in project activities. Setting up an output layer around gender equity may isolate gender, when what you want to do is integrate gender into all activities. Yet you cannot ignore this output as distinct, since it risks leaving out indicators for assessing performance on the gender front.

    This dilemma can be overcome by including separate cross-cutting objectives or principles. Sometimes these fit into the logframe in an integrated manner. If not, they need to be included in the project document and preferably as an attachment to the matrix. Being explicit about these cross-cutting objectives or principles is important in order to include them not only in activities but also in M&E.

    Table 3-3. Three options for adjusting the structure of the logframe matrix

    Type of Structure

    Description

    Advantages

    Disadvantages

    Standard objective hierarchy

    Four levels: 1 x goal, 1 x purpose, any number of outputs, any number of activities per output

    - Is very simple.

    - Is commonly used and understood.

     

    - Oversimplifies larger, multi-component projects.

    - Does not make project outcomes clear.

    Multiple purposes

    Four levels: 1 x goal, as many purposes as needed, any number of outputs per purpose, any number of activities per output

    - Maintains the standard four levels of the logframe matrix.

    - The standard is one purpose, so this may cause confusion.

    - Confusion between purposes and outcomes can still occur.

    Cascading logframes (objective hierarchies)

    Several interlinked, standard four-level logframes; each project component written up in a separate logframe; the purpose level = the component objective

    - Maintains the standard four levels of the logframe matrix.

    - Enables a focused, "sub-project" approach to management.

    - Doesn’t give an overview of cross-cutting objectives.

    - Focusing on integrative impact is difficult.

    - Is more complex.

    Extra layer(s)

    Five levels: 1 x goal, 1 x purpose, any number of key outcomes (or component objectives), any number of outputs per outcome, any number of activities per output

    - Makes a clear distinction between output, outcome and purpose levels, facilitating M&E.

    - Is consistent with standard LFA.

    - Some donors already use it.

    - More detail has to be included in the logframe matrix.

    Recognising the Importance of Outcomes

    Your project may have one output that is formulated as: "improve the capacity of the agricultural extension service and the skills of extension workers". Many projects use an indicator such as "number of extension workers trained". But if you want to manage for impact, you need to know the extent to which extension staff are using new skills in the field and, in turn, the extent to which farmers are developing and adopting improved agricultural practices. These are outcomes that occur after you have achieved your outputs (number of extension agents trained) and are necessary in order to have impact (increased productivity and income for farmers). If your M&E data show that although many extension workers have been trained, farmers are not adopting improved practices, then you can question what might be going wrong with your strategy of improving the extension service through training. This is why monitoring change at the level of outcomes is so critical in managing for impact. For IFAD, outcomes are also recognised as lower, purpose-level impacts. So, for communication and reporting reasons, it is important not to limit the documentation of impact to only the goal level of the objective hierarchy. Most people who use the standard LFA and matrix focus on tangible outputs. Outcomes should be included as indicators at the purpose level, but this is rarely done well. This is partly because the logframe was originally designed to focus on controlling the delivery of tangible outputs to be produced, such as kilometres of road built or area of irrigation scheme constructed. The three ways of dealing with larger projects, mentioned above, all help make the outcome level more explicit and detailed and also easier to monitor and evaluate.

    Back to Top

    3.4 Using the Logical Framework Approach

    3.4.1 Step One: Establish the General Scope and Focus of the Project

    The starting point for any project is to identify the general situation that will be improved, the likely primary and other stakeholders, the geographic scope of the project, the range of issues that will be addressed, and the likely length and expenditure of the project. Also find out what the community, government and potential funding agencies’ interests are in the project. This initial information provides the starting point for defining and guiding the detailed situation analysis and design steps. Some of this information will be outlined in the Country Strategic Opportunities Paper (COSOP). During this initial step, it is important to find out if the basic concept underpinning the project is feasible and if there is sufficient support from key stakeholders for it to be worthwhile to proceed to the next step.

    3.4.2 Step Two: Decide on the Planning Framework, Terminology and Design Process

    As already discussed, there are different planning frameworks and various approaches to the use of the LFA. In different countries, people will have had experience with different models and be used to a particular set of terms. It will help everyone if early on in the design process there is agreement about the approach to planning that will be followed, how the logframe will be used and what terminology will be used. Also define clearly what the design process will be, in terms of who will be involved, how and at what stage; what information needs to be gathered and how; and how the final design will be checked with key stakeholders. Box 3-10 lists key elements of participatory design based on IFAD experiences in Asia. This "designing the design process" step is often given very little thought and is the source of many problems that emerge during design and implementation.

    Box 3-10. Weaving together a participatory design phase (based on IFAD experiences in Asia)2

    • Establish a mentoring team – a group of committed, experienced and respected nationals who, on a voluntary basis, act as resource persons to advise the formulation process and champion the goals, strategies and approaches proposed by the project.
    • Undertake a participatory stakeholder analysis through a process of brainstorming with groups/individuals/institutions, grouping stakeholders, assessing their interests and impact on project success, assessing their influence and importance for project success, and outlining a strategy for their participation.
    • Establish the design team with national specialists from different professional sectors, relevant NGOs and government agency staff.
    • Train the design team in the use of diagnostic participatory tools and in drawing implications for project design from qualitative discussions with groups of stakeholders.
    • Review secondary data and key informant interviews.
    • Formulate the study design and analysis plan based on the information gaps you have identified.
    • Divide the project area into study zones, by identifying a number of relatively homogenous agro-ecological areas.
    • Undertake village-level problem identification and needs assessment through focus-group meetings and household interviews:
      • Assess problems: discuss problems, issues and concerns of villagers; assess causes and effects; identify which issues could relate to the project being planned; agree on criteria for prioritising problems; and prioritise problems.
      • Analyse options: discuss strategies and options proposed/desired by the community to overcome the problem situation.
      • Analyse alternatives: agree on criteria for comparing options to overcome problems and realise visions, then identify and assess alternative strategies/options available to reach the desired objectives.
    • Undertake a cross-cutting analysis, by agro-ecological zone and socio-economic stratum, to integrate analyses from different communities.
    • Hold design workshops involving different levels of stakeholders to work together on the logframe matrix:
      • Summary of objectives (objective hierarchy): develop project concept, vision, mission, results and activities.
      • Indicators: together identify which indicators capture and measure the different levels of changes the project is anticipated to affect.
      • Means of verification: agree on the sources of information to be used for monitoring impact.
      • Important assumptions/external factors: discuss the attitudes, behaviours, processes, trends, natural hazards/disasters, etc. outside the control of the project that could affect it positively or negatively.
    • Conduct continual surveys of primary stakeholder opinions to ensure that the consultation process and the interim results are as good as possible.
    • Hold national-level project reality-check and planning workshops to which a wide range of (primary) stakeholders are invited and during which initial ideas are presented and debated to consider different realities.
    • Draft the project proposal, based on workshop outputs, with a team of national and international experts.
    • Verify the draft project outline with the key stakeholders, particularly the intended primary stakeholders, in a series of discussions or workshops.

    3.4.3 Step Three: Undertake a Detailed Situation Analysis

    Situation analysis involves learning as much as possible about the project context and the interests and needs of local people in order to design a relevant project. This learning is best done with several groups of stakeholders. Box 3-11 provides a list of key situation analysis topics, questions and useful methods.

    The standard LFA focuses project planning on developing a problem tree for the situation. A problem tree works well for simple situations. However, problem-based planning fits with a more mechanical approach to development where projects are designed to "fix" problems rather than to facilitate local development processes. Furthermore, people see their future in terms of visions and aspirations – not just as problems. Analysing future visions helps identify opportunities for improvement and of successes that can be further developed. The LACOSREP water users’ association (WUA) programme in Ghana developed four complementary visions to describe the ideal WUA that they were aiming to help create.

    A good situation analysis will combine information gathering and analysis about the local context, expert advice and participatory processes such as participatory appraisals, community meetings and multi-stakeholder workshops. A creative and learning-oriented situation analysis will combine several methods (see Annex D).

    One result of a good situation analysis is that stakeholders have more insights about their situation and have better capacity to design a solid project. However, this will not be achieved in one community meeting. People’s perspectives evolve as they debate and listen. After a community meeting, subsequent discussion in people’s homes might have lead to adjustments if a meeting were held the following day. Take care that the situation analysis is designed as a series of events.

    Updating the situation analysis is critical for the M&E system. Note that a situation analysis is not the same as a baseline survey. Both are information-gathering exercises. But a situation analysis is more open-ended in terms of the themes and questions that are analysed, while a baseline survey only includes data that are needed to make impact-related comparisons. A baseline survey is undertaken after project design has been completed, while a situation analysis is undertaken as part of design.

     

    Box 3-11. Key themes, questions and methods (italicised, see Annex D) for a thorough situation analysis with stakeholders

    Stakeholders (stakeholder maps, institutional diagrams, secondary data)

    • Who are the local people likely to benefit from the project?
    • Who are the other key stakeholders?
    • How do different stakeholder groups interact?
    • What are the power relations between different groups?

    Problems and Issues (rich picture, conceptual maps, focus group discussions, historical analyses, secondary data, matrix ranking)

    • What problems or issues are central to the focus of the project?
    • What are the main problems or concerns of the different stakeholder groups and how do these relate to the focus of the project?

    Visions and Opportunities (rich pictures, role plays)

    • What changes would different stakeholder groups like to see the project bring about?
    • Generally, what visions, hopes or dreams do different stakeholders have and are there implications for the project?
    • What opportunities do stakeholders see for realising their visions?

    Biophysical Setting (maps, transects, field visits, seasonal calendars)

    • What are geographical characteristics of the project areas?
    • What are the climatic conditions?
    • What are the main forms of land use?
    • What are the environmental problems or risks?

    Organisations (institutional diagrams, network diagrams, flow charts, matrix ranking)

    • What are the important government, business and NGO organisations?
    • How effectively are these organisations performing?
    • How are the different organisations linked together (power relations, communications, joint work, competitors)?

    Infrastructure (resource maps)

    • What are the key infrastructure issues for the area?

    Law, Policy and Political Institutions (rich pictures, institutional diagrams, historical analyses, focused interviews, secondary data)

    • What legal factors are significant for the project?
    • What government policies and programmes are significant?
    • What are the main government and political structures and processes in the area?

    Economic (wellbeing ranking, daily activity charts, seasonal calendars, livelihood profiles, secondary data)

    • What is the economic situation of local people?
    • What are the main forms of economic livelihood?
    • What are the key characteristics of the local economy?
    • What are the market opportunities and constraints?

    Social and Cultural (historical analyses, focus group discussions, SWOT analyses)

    • What are the main social and cultural conditions relevant to the project?
     

    3.4.4 Step Four: Develop the Project Strategy

    With a good understanding of the situation, you are now ready to start developing the project strategy. This simply explains clearly what everyone hopes to achieve and how it will be achieved. A project strategy includes the objective hierarchy, implementation arrangements and resources required. This sub-section focuses on the objective hierarchy – column one of the logframe – central to the strategy. The objective hierarchy is a tree-type structure that maps out how activities and outputs contribute to the project purpose(s) and goal (see Figure 2-4 and the method description in Annex D).

    A project strategy will only work well if it is logical. This means that all the outputs required to achieve a particular purpose have been correctly identified and, in turn, that all the activities needed to deliver an output have been identified. For example, you cannot have as your output "production and certification of seed of improved varieties", without also including "testing and setting up private production of seed" and "training of ministry of agriculture staff for certification" as activities. Once the objective hierarchy is drafted, the logic needs to be tested (see Table 3-4).

    The standard LFA uses a very structured method of converting a problem tree into an objective tree or hierarchy. When working with project visions and in more complex situations where the problem tree becomes unwieldy in size, you could use a more open and iterative approach. The main steps in developing an objective hierarchy are outlined below and described in Annex B with a detailed example.

    1. Define the project goal. This should reflect the longer-term and highest-level impact to which the project will contribute.
    2. Identify the purpose(s). This is what must be achieved by the project in order to contribute to the goal. The purpose level generally describes major changes in behaviour or capacity. Because a project can contribute to the goal in many ways, the stakeholders will need to decide what is most worthwhile and feasible for this particular project. It helps to establish criteria to help make these decisions. It is good practice to include a separate purpose for project management. Here, key project management tasks can be included as outputs (see next step), such as staff management, financial management, plant and equipment maintenance, and M&E.
    3. Establish necessary outputs. For each purpose, identify what outputs are necessary for the purpose to be achieved. Think of it a bit like designing a car. If a key part is left out, like the wheels or the engine, it will not matter how good the rest of the car is – it still will not work. Also you do not want tractor wheels on a car or a motor-bike engine in a big tractor. In other words, make the outputs fit the real needs and avoid outputs that are not absolutely necessary. Any purpose can be achieved in several ways. Think creatively and analyse the advantages and disadvantages of different options before making a choice.
    4. Identify activities. Each output is delivered via a set of activities. At the initial project design stage, the best way of achieving purposes and outputs may be unclear, so activities may need future finalization and probably revision.
    5. Check the logic. Once the objective hierarchy has been drafted, use the logic testing questions in Table 3-4 for checking and finalisation.
    6. Allocate resources required for activities and develop an overall budget.
    7. Develop a work schedule for the main activities over the life of the project and establish key milestones.
    8. Establish the management and operational arrangements, with key responsibilities and working procedures.
    Table 3-4. Logic testing questions

    Level

    Logic Testing Questions

    Goal

    - Does the goal express some future desired state or higher-order impact towards which the project is contributing?

    - Does the goal help place the project in a wider context that provides the rationale for the project?

    - Is the goal narrow enough that it is meaningful given the scope of the project? Avoid goals expressed at an excessively general level.

    - Is the goal something owned and shared by relevant stakeholders?

    Purpose
    (if a single purpose)

    - Is the purpose a succinct statement of what the project will achieve overall?

    -Is the purpose realistic given the resources, time span and working context of the project?

    Purposes
    (if multiple purposes)

    or

    Outcome

    or

    Component objective
    (if an extra level is included)

    - Are the outcomes/component objectives the set of main outcomes necessary to achieve the purpose? In other words, if the outcomes/component objectives are achieved will the project purpose be achieved?

    - Do the purposes/outcomes/component objectives reflect the highest-level achievements of the project for which it can realistically be accountable?

    - Are the purposes/outcomes/component objectives realistic for the project to achieve during its lifetime?

    - Is there a set of practical actions that can be carried out to achieve each purpose/outcome/component objective?

    - Is one of the purposes/outcomes/component objectives dedicated to effective project management?

    Outputs

    - Do the outputs together describe the set of achievements that must be realised for the outcome/component objective to be realised? In other words, if the outputs are achieved will the outcome/component objective be achieved?

    - Are any outputs unnecessary to achieve the outcome/component objective or logically belong under another outcome/component objective?

    - Are the outputs realistic for the project to achieve during its lifetime?

    - Is there a set of practical actions that can be carried out to achieve each output?

    Activities

    - Do the set of activities for each output reflect the main actions that must occur for the outputs to be achieved?

    - Are any activities included that are unnecessary for achieving the outputs or that logically belong under another output?

    - Are there any activities that need to be split up and partly allocated to different outputs?

    - Are the activities all roughly equivalent in terms of their level of detail? In other words, are you sure that some activities are not more at an output level while others are at a task level?

    - Is the list of activities manageable (not too long)?

    For all levels

    - Are all levels understandable to project stakeholders and expressed as plainly and succinctly as possible?

    - Are any unnecessary means of achievement included?

    - Are there between three and about seven items for each of the (outcome/component objective, output and activity) levels?