|
|
|
This
Annex provides an example of the M&E matrix (see C.3,
Table C-2) that was introduced in Section
2 and explained in Section 5.
To
establish a good M&E system, you will need considerably more detail
about how to gather and use information than can be summarised in
the logframe matrix. Using the M&E matrix is one way of identifying
and documenting this additional information.
It
is important to recognise that an M&E matrix is only part of an
overall M&E plan, as it only considers what is needed to monitor
and evaluate the objective hierarchy. It provides detailed information
about how the goal or particular components, outputs and activities
will be monitored and evaluated. An M&E plan will include other
events that make it possible to understand the project context, reflect
and learn lessons.
Completing
the M&E matrix requires detailed knowledge of the project and
the project context. As the example in Table
C-2 is hypothetical, it cannot include the level of specific details
that would exist in a real project situation. Consequently, it is
more general than a real matrix would be. The example aims to provide
an overview of important aspects of the matrix, rather than present
a fully detailed matrix. The example is based on the logframe matrix
developed in Annex B.
Back
to Top 
C.1 Considerations When Developing
an M&E Matrix
As you
read through the M&E matrix example, there are several points
to keep in mind. These might be of use to you in understanding the
example matrix but also when developing your own M&E matrix.
From
data to lessons, understanding and decisions. When developing
the matrix, it is important to keep in mind how you plan to move from
data collection to explaining success or failure, creating understanding
about particular issues with stakeholders and, finally, making decisions.
In the example, the proposed annual workshop on food security will
enable you to reach a decision based on focused reflections. This
workshop will also allow you to identify lessons learned that can
inform next year’s work.
The
matrix at different levels in the objective hierarchy. In the
example, you will notice that at lower levels in the objective hierarchy
it becomes much easier to be very specific. For example, monitoring
the length of main and secondary irrigation canals dug is a more straightforward
task than assessing overall contribution to people’s livelihoods.
The further up the objective hierarchy you go, the more analysis and
synthesis of different types and sources of information are required.
Note that in the formal logframe matrix (see Section 3), indicators
and monitoring mechanisms are not entered into the logframe for activities.
Instead, resource inputs and costs are used. However, in practice
you will still need to monitor the activity level so you still need
to plan for this. The M&E matrix can be used to plan what is needed
for the activity level as well as for the goal level.
Triangulation
and validation. When deciding what data-gathering and analysis
methods to use, think about how you can ensure that data is reliable.
Triangulation means getting information about the same topic in a
number of different ways. Validation is what you achieve by then cross
checking the information. For example, from the participatory impact
monitoring (PIM) with women’s groups you might get feedback that a
particular new enterprise is very time-consuming in relation to the
income earned. If you get the same feedback from household surveys
and field observations of staff, you can be more confident of the
information. On the other hand, if you are getting conflicting information
from these different sources, then you will need to investigate further
to understand why there are differing opinions.
You can
also use the field records of agricultural extension staff or the
government as sources of valuable information for project monitoring.
However, positive aspects may be exaggerated and problems overlooked
– an inevitable human tendency. It is thus important to have methods
in place for checking and validating information.
Existing
information and data-gathering systems. Most projects will have
access to the already existing data-gathering and statistical systems
of the government or another agency. It is critical to see how these
can be used. It may be that for a small investment, existing systems
can be improved or modified to meet the project’s monitoring requirements.
Technology
use. Consider carefully where and to what extent information technology
can be effectively used. In the example, the increased areas of new
crops could potentially be monitored using remote sensing and geographic
information systems.
Specific
data vs. the big picture. Specific indicators provide fragmented
bits of information. To thoroughly understand the project, its successes,
failures and lessons, you need to build up the overall story. This
means integrating and analysing different pieces of information. The
"analysis, reporting, feedback and change" column of the
matrix provides a start for thinking about how this can be done.
Primary
data or secondary observations. Information about changes in household
capacity to meet education, health and housing needs could be gathered
in two ways. A detailed household survey could be conducted (primary
data) or community representatives and other key informants could
be asked about their observations (secondary observation). Generally,
primary data is more reliable but also much more time-consuming and
costly to collect. An important skill in completing the M&E matrix
is being able to balance the use of methods with the required level
of information accuracy and the available resources. Think carefully
about whether very detailed information is needed or whether an understanding
of the general trend is adequate. If all you need is a general picture,
then it might be possible to use qualitative methods in a cost-effective
manner.
Working
with specialists. To monitor some parts of a project may well
require specialist advice and input. In the example, it is proposed
that an economist be used to conduct a survey of the local economy.
Likewise, monitoring the yields of different agricultural crops is
a specialised task for an agronomist. There are now many people with
strong experience in monitoring microfinance schemes. Wherever possible,
try to draw on such expertise. The role of the M&E specialist
is to link this expertise to the project’s M&E plan and assess
how detailed the M&E needs to be for different parts of the project,
given resource and time constraints.
Aggregation
of field data. It will often be necessary to aggregate data from
different field locations. In the example, agricultural extension
staff are involved in recording changes in cropping patterns at district
and local levels. If these aggregation processes are to generate reliable
information, you will need to develop recording forms and aggregating
systems. You can detail this in column five of the M&E matrix.
Back
to Top 
C.2 Core M&E Activities
in the Example
Project
M&E will require you to use different methods to meet a wide range
of information needs. When developing a project M&E matrix, you
may feel as if you are drowning in the detail of methods for each
information need. However, a second look will reveal clusters of M&E
activities. While the M&E matrix requires you to specify information
needs and methods in detail, in practice they converge. This means
that one M&E activity can be used to meet multiple information
needs.
In the
M&E matrix example (see C.3, Table
C-2), you will find seven major recurring M&E activities (see
the list below). For example, a household survey will provide information
for a range of performance questions and indicators. Information from
such a survey may be combined with information from other sources,
such as participatory impact monitoring, to inform the annual project
review.
The M&E
matrix example focuses around seven major activities that form the
basis of this project’s M&E.
- Participatory
rural appraisal (PRA). Three PRAs will be undertaken: the first,
during the mobilisation phase; the second, one year prior to the
mid-term review; and the third, two years after project completion.
The PRA work will provide largely qualitative information about
the needs, issues and perspectives of different stakeholder groups.
The PRAs will be important in gathering information about unintended
positive and negative impacts from the project.
- Household
and farm surveys. Sample household and farm surveys will be
conducted to gather necessary baseline information, support the
mid-term review and conduct an evaluation two years after project
completion. In addition, more limited surveys will be conducted
on a yearly basis.
- Participatory
impact monitoring (PIM). Participatory M&E systems will
be established with key stakeholder groups involved in project implementation,
such as farmers’ groups and women’s groups. This will involve the
stakeholders in setting their own performance questions and questions,
developing monitoring systems and participating in training to support
implementation.
- Stakeholder
discussion groups. A series of stakeholder discussion groups
will be established around key project components and outputs. These
groups will help to analyse and review information, identify lessons
learned and make recommendations about necessary changes in the
project design.
- Government
statistics. Government normally collects a range of population,
economic and agricultural statistics relevant to project M&E.
Improvements in some aspects of this data gathering will be supported
by the project and the reliability of the data will be assessed.
- Field
observations. All project and implementing partner staff will
continually undertake systematic field observation. This will require
producing and using key questions relevant to their area of work,
training and information gathering and synthesis procedures.
- Special
studies. A range of special studies will be conducted, for example,
on changes in the structure of the local economy. Some of these
studies will involve external expertise. Where necessary, special
studies will be undertaken to provide further information on important
issues or opportunities that emerge from the regular monitoring
work.
Each
of these M&E activities needs to be well thought out and planned.
When planning the complementary use of the activities, it is particularly
important that you determine which ones can help provide information
for which specific performance questions and indicators in the matrix.
Back
to Top 
C.3 The M&E Matrix Example
Table
C-2 shows a partial example of an M&E matrix with annotations.
The matrix includes several different levels from the objective hierarchy
but has not been completed for the entire project. As mentioned above,
it is a hypothetical example and so the details are not as precise
as they should be in a real example. The purpose of the example is
to give a general idea of the types of issues that need to be considered
when developing an M&E matrix for a real project.
Table
C-1 provides annotations for the M&E matrix example. The numbers
in the table correspond to numbers in the matrix.
Table
C-1. Explanation of the issues highlighted in the M&E matrix example
|
Number
|
Issue
|
Explanation
|
|
1
|
How
to present information
|
Think
about how information needs to be presented for it to be meaningful.
Information should usually be presented in comparison to a target,
a prior state or the original state. For example, knowing only
the number of households who are more food secure is not as
informative as knowing the percentage and how the percentage
has changed over time.
|
|
2
|
Responsibilities
|
In
the example, responsibilities have not been included. However,
for a real project it is important to identify who will undertake
what aspect of the M&E work.
|
|
3
|
M&E
activities that provide information for several performance
questions and indicators
|
Some
M&E activities, such as a household survey, PRA or PIM,
can provide information for different evaluation questions and
indicators. The M&E matrix can help identify the different
types of information that need to be gathered from such activities.
The details of how these activities will be conducted and the
resource implications should be outlined separately to the matrix.
|
|
4
|
Combining
and analysing information
|
In
planning the M&E system, try to think as much as possible
about how different information can be combined and analysed
to report progress and also to explain success and failure.
|
|
5
|
Review
groups
|
Don’t
let good information sit on the shelf. The project can set up
different review or working groups or hold annual workshops
with key stakeholders to track progress and identify lessons
learned for different aspects of the project. These groups or
events can then feed their conclusions into the annual project
review process. The information needs of these groups can help
refine the overall monitoring and information-gathering strategy.
|
|
6
|
Reasons
|
Collecting
information about why part of the project is succeeding or failing
is just as important as monitoring what has been achieved. Collecting
information about reasons generally requires gathering and analysing
qualitative information.
|
|
7
|
Specialist
studies
|
An
economic study such as this is probably beyond the project team’s
capacities and would require input from an economist.
|
|
8
|
Technical
methods for monitoring
|
Some
indicators will require specialised technical methods related
to particular disciplines and specialisations, in this case
agronomy. It is very important that proper technical expertise
be used when developing such monitoring mechanisms.
|
|
9
|
Participatory
impact monitoring
|
Monitoring
yields at the field level directly could be very costly. It
may be possible to obtain adequate information through discussions,
in this case, with farmers’ groups.
|
|
10
|
Field
inspections to validate data
|
Validating
data is critical and field inspections by project M&E or
other staff is one way to do so.
|
|
11
|
Using
other sources of expertise
|
In
this case, a university has been used to undertake a specific
monitoring activity.
|
|
12
|
Setting
criteria
|
An
indicator will often include a quality, like "operating
effectively", that must be defined. In this case, it would
be necessary to identify the criteria for effective operation,
such as "regular meetings with 75% of members".
|
|
13
|
Monitoring
by implementing partners
|
Much
M&E can be undertaken by implementing partners. However,
it is important that they be involved in designing the M&E
system and be supported to carry out their responsibilities.
|
Table
C-2. Example of a partial M&E matrix
|
Goal:
Improved livelihoods for 35,000 poor families in the Rutunga Province
through increased food security and enhanced income-generating
activities
|
|
Performance
Questions and Related Targets
|
Information
Needs and Indicators
|
Baseline
Information: Requirements and Status (If Known)
|
Data
Gathering: Methods, Frequency, Responsib- ilities
|
Planning
and Resources: Forms, Planning, Training, Data Management, Expertise,
Responsib-
ilities
|
Information
Use: Analysis, Reporting, Feedback, Change Processes, Responsib-
ilities
|
|
For
whom has food security changed and in which ways?
75%
of families with food security under average seasonal conditions
|
Changes
over time in per cent of total households who are able to meet
minimum nutritional requirements (disaggregated according to type
of household, season and location)
|
Per
cent of households with food security under average seasonal conditions
at start of project - estimated at 40% from 2001 survey
|
Sample
household nutrition surveys: baseline, mid-term, project completion,
three years after completion
PIM
programme with sample villages and women’s groups (ongoing)
|
Nutrition
survey to be included in household survey (See separate details
on household survey methodology.)
Nutritionist
with M&E experience to provide specialist input (See separate
details.)

|
Household
survey information to be compared with feedback from PIM, PRAs
and field observations
Yearly
workshop with key stakeholders on food security
|
|
Reasons
for changes (for those now and those still not/no longer meeting
requirements)
|
Reasons
for insecurity at start of project
|
PRAs:
baseline, mid-term, project completion, three years after completion
PIM:
ongoing
|
See
details on PRAs and PIM.
|
As
above
|
|
How
has the purchasing power of target households changed – in particular,
for housing, education and health needs?
30%
increase in household expenditure on housing, education and health
|
Changes
in income, costs and expenditure patterns
(disaggregated
according to type of household and location)
|
Household
expenditure patterns at start of project
|
Sample
household surveys: baseline, mid-term, project completion, three
years after completion
PRAs:
baseline, mid-term, project completion, three years after completion
PIM:
ongoing
|
See
details on household surveys, PRAs and PIM.
|
Annual
and mid-term review of project with key stakeholders about the
project’s contribution to overall livelihood improvement in the
context of other initiatives in the province
|
|
How
have project interventions influenced the meeting of housing,
education and health needs?
|
Changes
expenditure patterns (disaggregated according to type of household
and location)
General
observations
|
Status
at beginning of project
|
PIM
Reporting
by NGO and agricultural extension staff
PRAs
|
See
details on PRAs and PIM.
|
Identification
of necessary changes and options for better collaboration with other
initiatives |
|
How
has the diversity and size of the local economy changed?
|
Changes
in types and value of products and services being exchanged
|
Nature
of local economy at start of project
|
Economic
analysis of local economy to be undertaken by specialist/ economist:
baseline, mid-term, project completion, three years after completion
Use
of government statistics
|
Development
of methodology and analysis by specialist/ economist
Strengthening
of government statistical methods for the province
|
Discussion
of economic changes and developments during annual project review
Establishment
of economic development task force
|
|
Proportion
of benefits of economic growth that stays local
|
|
How
have interventions affected the workloads, roles and well-being
of different household members (women, men, young, old)?
|
Changes
in workloads, roles and well-being disaggregated by gender, generation
and household type
|
N/A
|
Household
surveys
PRAs
PIM
|
See
details on household surveys, PRAs and PIM.
|
Regular
discussion with women’s advisory groups
|
|
How
equitably have different social and economic groups benefited
from the project’s interventions?
|
Analysis
of all above information in relation to household members and
household type
|
Identification
of particularly disadvantaged groups at start of project
|
Household
surveys
PRAs
PIM
|
See
details on household surveys, PRAs and PIM.
|
Discussion
of changes and developments during annual project review
|
|
Component
(purpose) 1: Agricultural production – agricultural production
increased, and diversified in a sustainable way
|
|
Performance
Questions and Related Targets
|
Information
Needs and Indicators
|
Baseline
Information: Requirements and Status (If Known)
|
Data
Gathering: Methods, Frequency, Responsib-ilities
|
Planning
and Resources: Forms, Planning, Training, Data Management, Expertise,
Responsib-ilities
|
Information
Use: Analysis, Reporting, Feedback, Change Processes, Responsib-
ilities
|
|
How
have the cropping patterns in the target area changed?
Area
of horticulture and vegetable production increased to 4,000 hectares
Area
of non-rice crops increased by at least 10% for small farmers
|
Changes
in cropping patterns disaggregated according to location and farmer
type
|
Land
use and agricultural activity information at start of project
(from department of agriculture)
|
District
record-keeping by department of agriculture field staff – quarterly
data and twice-yearly and yearly analysis and reporting
Remote
sensing
|
Improve
department of agriculture’s record-keeping procedures, train staff
and develop a new reporting format.
Install
a database and geographic information system.
|
Agricultural
production task force will be established. It will meet every
three months and review monitoring data. It will make a report
for the annual project review meeting, covering progress, lessons
learned and how any problems can be overcome.
|
|
How
much have farmers increased their yields of specific crops
60%
of farmers achieving 70% of target yields in years with average
seasonal conditions
|
Changes
in average yields per crop (disaggregated by location, year and
crop types)
|
Yields
at start of project
|
Sample
field surveys at harvest
PIM
by farmers’ groups
|
Identify
sample sites and train staff in field measurement.
Develop
participatory yield-appraisal and recording system with farmers’
groups.
|
|
What
innovations/ improved farming practices have been developed or
recommended? What level of adoption has occurred? What are the
reasons for adoption or non-adoption?
|
Types
of innovations/ practices that have been developed and recommended
Level
of adoption of different innovations
Reasons
for adoption or non-adoption
|
N/A
|
District
record-keeping by department of agriculture field staff – quarterly
data and twice-yearly and yearly analysis and reporting
PIM
by farmers’ groups
|
Improve
department of agriculture’s record-keeping procedures, train staff
and develop a new reporting format.
|
|
How
have the environmental impacts of agriculture changed?
70%
of farmers adopt at least one environmentally sustainable practice
Chemical
load in Besha River reduced to target levels
|
Level
of adoption of environmentally sustainable practices
|
Extent
of environmentally sustainable practices at start of project
|
District
record-keeping by department of agriculture field staff – quarterly
data and twice-yearly and yearly analysis and reporting
Field
inspections by project staff

|
Improve
department of agriculture’s record-keeping procedures, train staff
and develop a new reporting format.
|
|
Levels
of indicator chemicals
Silt
load
|
Levels
at start of project
|
Chemical
analysis of water samples every month
|
Give
monitoring contract to Ingsar University.
|
Results
will be discussed at provincial environmental committee.
|
|
Component
3: Institutional development – Output 1.1 farmer support groups
established and operating self-reliantly
|
|
Performance
Questions and Related Targets
|
Information
Needs and Indicators
|
Baseline
Information: Requirements and Status (If Known)
|
Data
Gathering: Methods, Frequency, Responsib-ilities
|
Planning
and Resources: Forms, Planning, Training, Data Management, Expertise,
Responsib-ilities
|
Information
Use: Analysis, Reporting, Feedback, Change Processes,
Responsib-
ilities
|
|
How
effectively are farmers’ groups supporting farmers to adopt new
crops and improved farming systems?
500
farmers’ groups operating effectively
|
Number
of farmers’ groups
|
Number
at start of project
|
Records
from department of agriculture field staff and from officially
registered groups receiving financial support from the project
|
Development
of record-keeping forms
|
Analysis
and discussion of success of farmers’ groups within agricultural
extension support group
|
|
Per
cent of target farmers actively involved with a farmers’ group
|
Per
cent at beginning of project
|
Recording-keeping
by farmers’ groups and aggregation and synthesis by M&E unit
|
Development
of record-keeping forms
|
|
Number
of farmers’ groups meeting criteria for a successful group
|
Number
at start of project
|
Reporting
by department of agriculture field staff
Qualitative
survey of farmers’ groups every two years
Record-keeping
by supporting NGOs
|
Establishment
of criteria for a successful group
Training
staff to undertake a farmers’ group survey
Development
of record-keeping system for NGOs
|
|
Extent
to which farmers’ groups have influenced adoption of new practices
|
Historical
role of farmers’ groups
|
Interviews
with key informants
|
|
|
Component
5: Infrastructure built and maintained – Output 5.1 roads extended
and maintained
|
|
Performance
Questions and Related Targets
|
Information
Needs and Indicators
|
Baseline
Information: Requirements and Status (If Known)
|
Data
Gathering: Methods, Frequency, Responsibilities
|
Planning
and Resources: Forms, Planning, Training, Data Management, Expertise,
Responsibilities
|
Information
Use: Analysis, Reporting, Feedback, Change Processes, Responsibilities
|
|
How
has the road infrastructure improved as a result of project interventions?
150
km of main roads and 200 km of secondary roads
|
Kilometres
of new main roads constructed per year
|
N/A
|
Record-keeping
from finalisation of construction contracts
|
|
Review
of road construction programme during annual project review
|
|
Kilometres
of secondary roads constructed per year
|
N/A
|
Record-keeping
from finalisation of construction contracts
|
|
|
Change
in driving time between key locations
|
Driving
times at start of project
|
Interview
with key informants
|
|
|
Change
in road use
|
Level
of road use at start of project
|
Road-use
survey: baseline, mid-term, project completion, three years after
completion
|
Design
of survey
|

Download
PDF Version (169 KB)
|