Completion evaluation
The IFAD Office of Evaluations and Studies carried out a Completion
Evaluation (CE) of the IFAD-financed North West Agricultural Services
Project (NWASP) in Armenia from February to June 2001. The IFAD loan to
finance the Project was identified in 1994, approved in December 1997.
The loan became effective in April 1998 and was scheduled to close in
December 2002. However, due to rapid implementation, Project activities
and disbursements were more than 90% complete at the time of the evaluation.
The Project was subject to a Completion Evaluation because it is part
of an IFAD pilot programme for direct supervision. The Evaluation gave
IFAD the first opportunity to analyse the experience of direct supervision.
It also provided an opportunity to draw lessons in both water management
and rural finance for reference in the design and implementation of other
IFAD projects in Armenia and elsewhere in the region.
The
evaluation
The IFAD approach to evaluation included the creation of a Core Learning
Partnership (CLP) of key project stakeholders that helped to set the objectives
and key questions for the Evaluation. The CLP reviewed the draft Evaluation
Report and participated in a Workshop held in Tsakhkadzor in August 2001
where it concluded an Agreement at Completion Point that detailed those
recommendations and follow-up for which there was a consensus.
The objectives set for the Completion Evaluation were to: (i) learn
how, and to what the extent, the project achieved its overall objective
to improve the living conditions of the target population; (ii) determine
the impact that direct supervision of NWASP by IFAD has had on NWASP and
on IFAD; and, (iii) provide feedback on NWASP project outcomes that can
help partners associated with the future Agricultural Services Project
successfully achieve their objectives. The key questions posed by the
CLP were:
- How did the Project change the living conditions of the target population
in terms of income, production and food security?
- To what extent were the designs of the various components relevant
to the needs of the target group?
- How effective were implementing agencies in reaching their physical
objectives?
- How efficient were the implementing agencies in achieving the maximum
level of benefits with the resources allocated to them?
- To what extent can the benefits of the various components be sustained
after project completion?
- What were the costs and benefits of Direct Supervision of this project
by IFAD?
With respect to the dissemination of Evaluation findings and recommendations,
the CLP placed a high priority on using the Evaluation to create a greater
awareness of the project outcomes and lessons within higher levels of
Government.
A participatory approach was used wherein stakeholders, including
several project beneficiaries and implementing agency staff, served as
the Evaluation Team working in the field under the guidance of a Team
Leader. In addition, the evaluation included a Socio-Economic Survey that
repeated interviews with the same 699 households interviewed for the Socio-Economic
Baseline Survey in August 1998 and again in late 1999.
Altogether, the sources of information for the evaluation included:
(i) more than 300 beneficiaries, leaders of communities, and grassroots
organisations in 48 communities interviewed during evaluation fieldwork;
(ii) the 699 households interviewed for the formal socio-economic survey;
(iii) key informants from implementing agencies interviewed by the Team
Leader; and, (iv) IFAD staff and consultants responsible for project supervision
who responded to a questionnaire or were interviewed.
At the end of the fieldwork, participants in the evaluation and agency
staff rated the effectiveness of the evaluation. In each marz work concluded
with a briefing for officials and community and implementing agency leaders
presented by beneficiary members of the Evaluation Team. A debriefing
/ wrap-up seminar was held in Yerevan attended by high-level Ministry
officials on 6 April 2001. At the seminar reports were presented on each
project component by beneficiaries, and on overall preliminary conclusions
by the Team Leader. Finally, the evaluation processes concluded with a
Workshop held in Tsakhkadzor in August 2001 with the drafting of an Agreement
at Completion Point that includes those recommendations and follow-up
upon which there is a consensus.
Back
to Top
The
project design
The goal of NWASP was to improve the living conditions of the
target population in terms of higher levels of production, income and
food security. It operates in three Marzer: Aragatsotn, Lori and
Shirak in the north-west. The Ministry of Food and Agriculture (MOFA)
is the project executing agency. It established a Project Co-ordination
Unit (PCU) based in Yerevan that implemented the project through six agencies:
Water Management Services (WMS) section of the Irrigation Rehabilitation
Programme (IRP), the Agricultural Cooperative Bank of Armenia (ACBA),
an international NGO called the Armenian Technology Group (ATG), and an
Armenian NGO, SHEN.
The estimated total project cost was USD 13. 4 million of which USD
12. 9 million was funded by IFAD and USD 0.5 million by the GOA. As at
1 March 2001, approximately USD 12 million had been disbursed. Project
implementation activities were scheduled to end in June 2001, approximately
18 months ahead of schedule.
The target population numbered about 335 000. It was composed largely
of small farm households with an average farm size of 1.3 ha. Many of
these had been part of the commune/state farm system before the privatisation
of farming land. Some were headed by individuals allocated plots of land
after being dislocated from industrial enterprises that closed down when
Armenia became a separate republic. Benefits were expected to reach some
9 500 households about 13% of the total. Activities in the community development
component were to be directed to the poorer villages. In the Credit component
the aim was to assist to women take up to 30% of loans.
The project had four components:
Irrigation rehabilitation: to rehabilitate irrigation water supply and
control structures; and help improve management, operations and maintenance
(O&M) of the irrigation systems through water user associations
Rural credit: to support ACBA in increasing its lending
services to farmers in the three marz, including the provision of capital
and on-lending resources, building and equipping branch offices and development
of village associations (VAs) as shareholders in ACBA to organize borrowers
at a village level
Agricultural and livestock development: to produce good
quality seed and provide veterinary services for livestock production
Community development: to assist the poorest villages
to identify, plan and implement their own priority activities using participatory
techniques.
Back
to Top
The
key questions
How did the Project change the living conditions of the target population
in terms of income, production and food security?
Findings with respect to income and living standards from the survey
were difficult to interpret. The Survey found little difference between
beneficiaries and control group households in the increases in the value
of their average total income (cash and own consumption) between August
1998 and March 2001. At the time of the survey, farmers were experiencing
drought conditions and approximately 80% of beneficiary households reported
incomes below the national poverty line. However, they fared somewhat
better than control group farmers, 90% of whom reported to be below the
poverty line. Both groups have experienced a sharp decline in living standards
from the time of the repeater survey in October 1999 when only 6% of beneficiaries
and 18% of control group members were below the poverty line.
The survey found significant changes in the agricultural production
levels of households that participated in NWASP compared to those from
the control group who did not participate in the project. For example,
for a typical beneficiary household output in cereals and potatoes increased
by more than 66%. Whereas, output for control group households stayed
the same or fell with respect to those two crops. Outputs of vegetables,
fruits and fodder were also higher for beneficiaries than for control
households. Overall, the total value of their output was 30% higher than
the value of agricultural output of the control group.
With respect to food security, the percentage of households with
a three-month supply of food in storage fell for both the beneficiary
and control groups. This was largely due to on-going drought conditions
and seasonal difference in the period during which data was collected.
However, the drop in beneficiary households with such stocks was only
3% while it was 20% for the control group. Food intake has also become
more regular among beneficiaries. At the time of the baseline survey 19%
of households reported skipping daily meals. That figure has now dropped
to 10% among project beneficiaries, and it is 17% for the control group.
The survey showed that 66% of women and children consumed three meals
per day in the four months preceding the survey, while only 50% did so
at the time of the baseline survey in August 1998.
To what extent were the designs of the various components relevant to
the needs of the target group?
The Evaluation found that beneficiaries were largely satisfied with
the designs of each component, subject to constraints imposed by funding.
Communities indicated that inadequate irrigation resources were the major
constraint to improved living conditions. Moreover, irrigation improvement
had widespread relevance, providing benefits in a relatively equitable
fashion to a cross-section of the community. Because design and implementation
was guided by community groups it provided a strong link to community
needs.
The same held true for the community development component. The processes
designed were relevant. Moreover these processes allowed communities to
demand and effect a shift in the types of activities selected the project
would support. Yet, the shift created by the new activities chosen by
community Civil Action Groups was not entirely positive. It re-allocated
project funding from public to private goods. The evaluation team observed
that in these cases most of the direct benefits from the project went
to a very small number of beneficiaries who owned agro-enterprises that
received grants. The responsible NGO argued that the indirect benefits
to the community from the new enterprise in terms of economic activity
and employment offset this seeming imbalance.
The credit component was relevant to the needs of many members of
the target group. However, it was implemented in such a way as to be accessible
to very few. Limited funds were effectively rationed by relatively stringent
collateral requirements. In this way the project helped build a sound
financial institution that, in future, is likely to reach further down
to smaller, higher risk farmers. However, during the project implementation
period this group did not benefit from project-supported financial services.
The seed component was designed to meet the expected need for certified
cereal and potato seed that would allow farmers to achieve higher crop
productivity in rehabilitated irrigated fields. The relevance of this
component is called into question by the fact that effective demand for
these seeds was low. This was found to be due to: (i) farmer uncertainty
over the suitability of imported cereal varieties for local growing conditions;
(ii) local consumers taste; and, (iii) low levels of farmer incomes
that have prohibited purchase of higher cost improved seed.
How effective were the implementing agencies in reaching their physical
objectives?
The Project was very effective in achieving most of the physical
targets set in the logical framework. As shown below, implementing agencies
even surpassed irrigation, credit and seed component targets.
|
Component/Sub-component |
Indicator |
Planned at Appriasal |
Actual April 01 |
| Irrigation and Water Management |
Water Management
|
Field offices
established/upgraded |
3 |
3 |
| WUAs formed
(days) |
50 |
58 |
| WUA training |
150 |
174 |
|
Irrigation Rehabilitation
|
Designs (scheme)
carried out |
50 |
54 |
| Schemes rehabilitated |
50 |
50 |
| Schemes rehabilitated
(ha) |
6 975 |
17 361 |
| Agricultural Credit |
| |
Village associations
established |
100 |
228 |
| Branch offices
established/upgraded |
3 |
2 |
| Loans extended
(no.) |
6 108 |
7 466 |
| Loans extended
(USD) |
4 095 800 |
5 462 151 |
| Loans repaid/recovered
(no.) |
6 108 |
4 924 |
| Loans repaid/recovered(USD) |
4 095 800 |
3 505 637 |
| Loans extended
to women (no.) |
1 832 |
698 |
| Loans extended
to women(USD) |
1 228 740 |
527 209 |
| Community Development |
|
|
Contracts to
participating communities |
100 |
81 |
| Community projects
completed |
100 |
61 |
Crop &
Livestock Development |
|
Seed multiplication
|
Farmers engaged
in seed multiplication |
800 |
367 |
| Area planted
for seed multiplication (ha) |
1 200 |
1 820 |
| Farmers repaid
seed equivalent |
n/a |
284 |
Regulatory services
|
Certifications
made |
n/a |
0 |
| Seed testing
laboratories rehabilitated |
4 |
4 |
|
Animal health care
|
Veterinary
laboratories rehabilitated |
3 |
3 |
| Training
courses held |
4 |
1 |
| Disease diagnostic
tests undertaken |
70 |
0 |
How efficient were the implementing agencies in achieving the
maximum level of benefits with the resources allocated to them?
Beneficiaries rated project efficiency as high. Quantitative data
also shows that the level of efficiency of the implementing agencies was
quite high in terms of transforming financial inputs into physical outputs.
This was especially true of WMS and IRP in irrigation, but also of ACBA
in credit and to some extent ATG in seed supply. As noted above, funds
made available in the Project were managed in such a way as to realize
output levels that were higher than forecast at appraisal, in less time.
The number of hectares covered in irrigation rehabilitation was, for example,
250% of what was planned. Likewise, the value of funds lent was 133% of
planned levels. The Project was able to undertake more training days with
allocated funds, establish more village associations for credit, and plant
more hectares for seed multiplication.
However, these results need to be interpreted with caution. While
at least partly attributable to good management, other factors came into
play. They can be partly attributed to over-estimation of costs at appraisal,
exchange rate fluctuations, and contributions in-kind from beneficiaries
that exceeded expectations. In the case of lending, the good management
that led to high repayment levels and the resultant possibility of increase
the number of loans was the result of very conservative loan screening
criteria. This had the undesired consequence of excluding beneficiaries
the Project was designed to reach in the project area.
To what extent can the benefits of the various components be
sustained after project completion?
The Evaluation found that the rapidity of project implementation
which clearly contributed to its effectiveness and efficiency could potentially
have a negative effect on the sustainability of its benefits: early project
closure could cut short support for village level organizations created
by the project. Many organizations, after only three years of project
implementation, may not have had sufficient time to develop into mature
institutions able to function on a sustained basis.
Irrigation Component Without a strong commitment from GOA to work
with and support the WUAs, and translation of commitment into action,
the benefits from irrigation rehabilitation investments will not be sustainable.
Due to the dry seasons and problems in dealing with the water supply companies,
WUAs currently face difficulties raising the funds from water charges
to both pay for bulk water supply and fund O&M operations. Commercial
farmers will be able to fund water charges. However, smaller non-commercial/subsistence
farmers potentially half the farmers in the project area - are
unlikely to have acquired surpluses to pay the full costs. Inability to
pay could well undermine the current model of irrigation water supply
and management of irrigation O&M in Armenia.
Agricultural Credit Using Village Associations, ACBA has developed
processes and procedures for managing a rural credit programme providing
a range of credit from small seasonal loans of USD 100200 through
to longer term loans of up to USD 5 000. ACBA itself is providing agricultural
loans for up to USD 40 000. Thanks to sound financial management and successful
on-lending practices, there is every reason to expect that current levels
of lending in Lori and Aragatzotn will continue. However, expansion in
lending will be constrained by the ACBA levels of capital and access to
additional credit lines. In future, savings mobilization from rural communities
through the banking network created by the Project will be important for
sustaining and expanding banking services.
Community Development Ongoing benefits from social development activities
will depend on the energy and enthusiasm of the Civic Action Groups to
mobilize resources for further projects to assist their communities. SHEN
monitoring reports indicate that half of the groups created have taken
steps to achieve this. Yet, without continuing interest and support from
SHEN or a similar agency, this energy is likely to dissipate. The sustainability
of the new economic development projects funded by loans from SHEN will
depend on the entrepreneurship of the individuals who own the businesses
that received them.
What were the costs and benefits of Direct Supervision of this
project to IFAD?
Actual expenditures on IFAD direct supervision and follow-up of this
project were approximately USD 65 000 per year. About USD 45 000 was covered
by the IFAD regular budget and USD 20 000 came from extra-budgetary resources
in the form of supplementary funds. The Country Portfolio Manager and
Programme Assistant estimate that roughly 40% of their time was allocated
to direct supervision of the project. Other IFAD colleagues indicated
that this might be an underestimation of actual CPM and PA time dedicated.
If this cost - normally covered in payments to Cooperating Institutions
- is accounted for, then overall costs increase to USD 139 000. These
costs, in terms of staff time, were borne by the CPM and Programme Assistant.
They were incurred at the expense of other projects and IFAD duties that
received less of their attention and at their own personal expense. The
assignment of an Associate Professional Officer to assist the CPM added
human resources (and costs), attenuating the burden on the CPM and PA
for part of the project implementation period.
Comparison with other projects directly supervised by IFAD from among
the current pilot programme and eventual second generation
IFAD supervised projects will be needed in order to determine the extent
to which staff time costs were high because of the first time or path-breaking
nature of durect supervision in the NWASP case. However, while costs incurred
in the recruitment of consultants for implementation support (in this
case about two thirds of the USD 65 000) could be treated as variable,
the basic cost to IFAD of direct supervision in terms of staff time is
fixed. And, experience form this project would indicate that it is likely
to remain higher than originally expected, even after experience is gained
in the related processes. This will be due to the numerous time consuming
tasks in loan administration, loan supervision and implementation support
and because of the nature of the close working relationship that develops
between the project management and the IFAD staff.
The most apparent benefits of direct supervision to the project were
derived from the responsiveness of IFAD to project needs. This was manifest
in rapid replies to queries from the PCU related interpretation of the
Appraisal Report and IFAD procedures with respect to procurement, recruitment
and other disbursement issues. It was a significant contributing factor
to the quick pace of project implementation and full disbursement before
the expected closing date.
Project implementing agency staff were generally appreciative of
the quality of technical support provided by IFAD in project implementation.
This is attributable, at least in part, to IFAD direct supervision as
it heightened IFADs understanding of project needs for support
as well as its commitment to efficient provision of support. The project
also appreciated the continuity of working with one interlocutor from
design through implementation. Regrettably, the expected learning benefits
to improve performance were not shared with IFAD generally, but rather
confined to the staff directly concerned. Moreover, for the IFAD portfolio,
the learning was limited as a result of the fact that many of the same
individuals both staff and consultants were responsible
for both project design and implementation. There was an advantage to
this in that the individuals involved could learn, through direct observation,
the outcomes resulting from their own decisions made in project design.
That is, they could see for themselves what worked and what didnt.
However, the main disadvantage was that no constructive critical review
or questioning of decisions took place outside of a very small circle
of individuals. Hence, there was a lost opportunity for them to learn
from the perspectives of other professionals within IFAD who have different
skills and experiences to draw on or who were not as closely caught up
in the everyday project matters.
Back
to Top
Project
performance by component
Irrigation rehabilitation and water management.
A total of 322 km of canals, pipes and associated control structures were
installed bringing 19,688 ha of previously irrigated land back into full
production. The Government adopted the WUA model developed by the Project
for replication throughout Armenia. However, without the training courses
and support services provided by NWASP, it has been considerably less
successful outside the project area. Three federations/unions of WUAs
have been formed in the project area to provide a link between users of
common supply channels and to bring a united voice to work with government
and water supply companies. Despite recent very low rainfall some systems
were still able to achieve higher yields, even with limited water supplies.
WUAs have had some success in collecting water charges where irrigation
water has been available. However subsistence farmers may not be able
to generate enough cash income to pay water charges which will compromise
the whole WUA / O&M funding model. Communities are still confusing
WUA charges with government tax collection.
Rural credit. The formal credit component of the
Project has been implemented through ACBA using collateral-based lending.
In 2000, 2 314 loans totaling USD 1 635 637 were disbursed to clients
in project communities. ACBA successfully established branch offices in
the three project marzer. IFAD loan funds provided to ACBA as a grant
allowed it to increase its capital base and expand lending to more farmers
and small business clients. While ACBA business suffered from serious
mismanagement in Shirak, the contrary was true in Lori and Aragatsotn
where loan repayments were close to 100%. This too allowed for expanded
lending beyond levels forecast in the Appraisal Report. Village Associations
were created in 186 project villages with 5 225 members to identify borrowers,
screen applications and provide joint security for loans. Credit was short
term and initially targeted at crop inputs, but is now being used to purchase
large livestock. A significant weakness in design, related to the prevailing
financial sector environment in Armenia, was the absence of a companion
programme to mobilize savings in communities. In addition, ACBA proved
unwilling to reach out to borrowers without collateral, despite IFAD Supervision
Mission pressure to do so through group lending.
Community development. Villages in each marz based
on poverty criteria were selected and provided with assistance to identify
and undertake social and economic development projects. CAGs were encouraged
to identify other social development projects that could be proposed to
other organizations for funding. Sixty-one social development projects
were completed. The majority were water supply projects, as these were
achievable within the project-defined funding limit of USD 10 000. Half
the CAGs have initiated further activities in their villages. At the request
of communities, emphasis shifted from social development to group economic
development projects, such as rehabilitation of machinery stations. It
shifted again, in late 2000, to the provision of loans by SHEN to individual
farmers to provide employment opportunities in their communities. Nineteen
such activities were funded.
Seed production services. ATG efforts have been
directed to increasing the supply of certified and graded cereal seed
with some support to potato and alfalfa seed production. More than 900
t of elite and first generation seed has been produced on over 400 ha
but has been limited by the dry seasons. Informal arrangements to distribute
this seed to poorer farmers have been very successful using seed swapping
and buybacks to overcome their inability to pay for the seed. ATG has
also purchased large quantities of seed for distribution in other parts
of Armenia to the benefit of USAID food security programmes. Yet, the
seed production programme has been clouded by disagreements over consumer
acceptance of US wheat varieties and the need to use higher seeding rates
for Armenian and Russian seeds. Performance is declining in the seed and
input credit programmes operated by ATG. Seed testing equipment provided
to MOFA cannot be fully utilised because funds were not allocated to training.
Animal health. Inputs were financed by the IFAD
loan to upgrade the marz veterinary laboratories. These have not been
accompanied by the government regulation required to support private veterinarians.
Therefore the project could not provide the planned equipment and training
to the private sector. Nonetheless, private veterinarians are ensuring
essential vaccination and animal health programmes in the project area.
Project coordination. The performance of the PCU
and project coordination in general has been exceptionally good. Excessive
audit and checking on PCU activities by various government authorities
had high costs in terms of staff time and would appear unjustifiable.
Good management combined with the use of the SOF provided before the loan
signature and good support from the IFAD Country Portfolio Manager (CPM)
led to not only meeting but also exceeding targets in virtually all components,
even ahead of schedule. The Project Coordinating Council (PCC) met regularly.
However, project design did not include a formal coordination or planning
group at the level of individual marzer, which would have permitted better
decentralized bottom-up planning. In implementation, the inputs of the
marz M&E coordinators, who all had very close relationships with the
marz governments compensated for this.
Back
to Top
Project
impact
Each of the project components led to successful outcomes. As noted
above in paragraphs 13.-15., there have been improvements for beneficiaries
in terms of production and food security, even in the face of declining
per capita income levels for beneficiary and control groups. However,
it is very difficult to draw definitive conclusions about the project
impact at the household level due to: (i) the short time that has elapsed
between surveys; (ii) differences in timing, within the agricultural calendar,
of the surveys (August 1998, October 1999 and March 2001); and, (iii)
incidence of drought between the first repeater survey and the survey
done for the Evaluation.
More than 36 000 households directly benefited from some or all project
activities - roughly 250% of the 9 500 households the project was expected
to reach. More than 20 000 families have benefited from the irrigation
rehabilitation activities servicing 18 700 ha. A further 18 000 benefited
from the 78 social and economic development projects facilitated by SHEN.
ACBA credit activities included 7 466 loans. In the year 2000, for example,
it reached 2 400 households with credit for farming crop inputs and livestock
to improve their businesses and take better advantage of upgraded irrigation
facilities.
Apart from household level impact with respect to food security and
production levels, project impact on households and communities is detectable,
in terms of social, economic and technical practices. Cropping patterns,
cropping practices, areas planted and yields have changed because of the
project, for example, cultivation is intensifying and land parcels are
becoming larger. Economic activities, such as marketing have changed -
a lower proportion of food crops are being marketed and credit is being
used to purchase inputs. Social behavioral patterns are changing, as a
result of the project people are forging new village-level working relationships
in community organisations that replace old politically oriented ones.
However, the project has been operating for only three years and it is
one of many new forces of change in the project area, not all changes
observed can be fully attributable to the project.
Based on Evaluation observations the greatest long term impact on
the communities served by NWASP are likely to come from the development
and support inputs provided to grass roots organizations. The 186 ACBA
village associations, 58 water user associations, and 55 civic action
groups created in the project area have begun to develop the capacity
to sustain current benefit levels and undertake further activities. However,
they have not yet had time to take root and are not fully prepared to
assume their responsibilities for physical outputs. From this point of
view, project phasing was sub-optimal and future benefit streams will
be in jeopardy if the project is closed prematurely because funds are
fully disbursed.
To consider the beneficiary point of view, the Evaluation team compiled
responses obtained at the village level whereby the beneficiaries rated
the impact of project activities by component, based on their own subjective
definitions of impact. These ratings, shown below, were combined with
beneficiary ratings of project according to criteria set by the CLP and
specified in the key questions of the evaluation.
Evaluation Teams Synthesis of 32 Community Assessments of Project
Activities
| Marz |
Assessment
of village activities |
Assessment
of Grassroots Organizations |
|
Impact |
Relevance |
Efficiency |
Effective. |
Sustain. |
Relevance |
Effective. |
Sustain. |
| Community
Dev. |
|
|
|
|
|
|
|
|
| Shirak |
2.7 |
2.7 |
2.7 |
2.5 |
2.7 |
3.0 |
2.7 |
2.7 |
| Lori |
2.9 |
2.3 |
2.9 |
2.9 |
3.0 |
2.6 |
2.1 |
2.0 |
| Credit |
|
|
|
|
|
|
|
|
| Shirak |
1.7 |
2.4 |
1.9 |
2.0 |
1.9 |
2.1 |
1.5 |
1.7 |
| Lori |
2.6 |
1.8 |
2.1 |
2.6 |
2.0 |
2.4 |
2.0 |
2.1 |
| Seed |
|
|
|
|
|
|
|
|
| Shirak |
2.0 |
3.0 |
2.5 |
2.1 |
2.1 |
n.o. |
n.o. |
n.o. |
| Lori |
2.4 |
1.9 |
2.5 |
2.4 |
2.2 |
n.o. |
n.o. |
n.o. |
| Irrigation |
|
|
|
|
|
|
|
|
| Shirak |
2.6 |
2.6 |
2.6 |
2.5 |
2.7 |
2.8 |
2.3 |
2.6 |
| Lori |
2.9 |
2.6 |
3 |
2.8 |
2.6 |
2.9 |
2.3 |
2.8 |
|
( Ratings levels 0 = none, 1 = low, 2 = medium, 3 = high |
Back
to Top
Recommendations
Project closure
- The impact and effectiveness of NWASP activities should be monitored
up to the original planned completion date of December 2002. This should
focus on the performance and sustainability of the grassroots organisations
created through NWASP.
Irrigation
- Fully transparent information on the ways that water fees are set,
the ways that fees collected are allocated among concerned agencies,
and the ways that fees are used by those agencies should be made available
to all water users through water user associations.
- An independent study of the cost of water delivery should be immediately
undertaken.
- On the basis of the results of study there should be a: (i) review
of government policies on the allocation of investment resources to
irrigation infrastructure; and, (ii) re-examination of the viability
of subsistence and small-scale farms given the costs of water that they
may have to bear.
- Current policies regarding use of loan funds for civil works should
be changed to allow water user associations to supervise and undertake
rehabilitation of schemes with technical backstopping by concerned government
agency and monitoring by the project.
Credit and finance
- New approaches to providing financial services to borrowers without
collateral should be tested.
- Involvement of non-financial institutions should be limited to: (i)
support borrowers in accessing and using finance; and, (ii) support
banks in loan screening, disbursement and repayment monitoring.
- Financial services in rural areas should be expanded to include savings
and establish links between savings and lending practices.
Seeds
- Testing of new cereal varieties should be done by GOA research stations,
with links to producers.
- Grassroots seed producer organisations, based on the models of Vardablur
and Gulagarak, in Lori should be initiated at district level in each
marz to allow growers to share technical and market information.
Community development
- Community development agencies should not be directly involved in
lending activities as such, especially for loan-sizes already handled
by existing financial institutions.
- Community development agency involvement in financial service delivery
should be limited to support microfinance activities not normally handled
by banks.
- The approach to the use of grant financing to reduce poverty through
community development should be broadened. If communities wish to focus
on employment generation, for example, a range of activities such as
training and assistance to entrepreneurs in preparing business plans,
accessing formal institutions, or investing remittances could be considered.
- The NWASP model of developing and supporting grassroots organisations
such as the community action groups, water user associations and village
associations, to assess peoples priorities, plan, and implement
activities should be used wherever possible.
- Assigning local NGOs the responsibility for working with projects
to develop these grassroots organisations should be considered.
Information
- All projects should include communications programmes to provide
target groups with information they need to understand project objectives
and activities. Widespread information campaigns should start during
project design and continue throughout implementation.
IFAD supervision of IFAD loans
- There should be a monitoring system to analyse financial and human
resource costs to IFAD of direct supervision.
- There should be explicit ways of sharing, within IFAD, the knowledge
that it acquires through direct supervision.
- A system of checks and balances should be created whereby responsibility
for design, supervision, monitoring, and approval processes are shared
rather than vested in a single staff member as at present.