|
Objectives
The project aimed at raising the living standards of a rapidly
increasing population while arresting land degradation resulting from
an influx of refugees from the drought-stricken northern regions.
Activities
The project intended to:
- increase small farmers' incomes through increased production of grains
and pulses by providing farm inputs and water supplies;
- extend technology identified under the first phase of the project
or to be developed under the second phase;
- increase livestock output by creating an effective veterinary service;
- conserve range and develop pasture;
- adopt farming systems to arrest ongoing soil and range degradation;
and
- introduce a system of land tenure.
OutcomeFollowing a difficult start, the objectives and focus of
the project were revised in 1988 when it essentially abandoned the aim
of introducing fixed land tenure. The earlier objectives of building settlements
were frozen and priority was given to the generation and extension of
new technology to benefit the majority of farmers.
The project achieved important results in the field of animal
health.
Access
to inputs and infrastructure
| Planned |
|
Achieved |
| Continue the track improvement
programme, constructing 24 Irish bridges, six culverts and 37
km of raised earth embankments.
Build 15 new water yards at new sites on the settlement
programme; rehabilitate an additional 54 water yards; and assist
in the establishment of a comprehensive ongoing maintenance system
for the 224 water yards in the project area. |
|
The project fell short
of most of its targets in the track improvement programme, constructing
14 Irish bridges, 12 culverts and only 6 km of raised earth embankments.
The project achieved most of its physical objectives
in terms of water development. It rehabilitated 54 water yards,
as envisaged at appraisal, but was only able to build six new
yards. The maintenance programme target was not attained, and
the overall condition of the water yards in the area deteriorated
during project implementation, as shown by the decline in annual
output. The project also erected or replaced 30 new water tanks.
|
Range
management
| The poor
condition of the rangeland is the result of communally owned
grazing, privately owned livestock and owners competing for
the available grazing. Under these circumstances, the communal
responsibility for preserving a balance between the supply and
demand for rangeland is lost. |
| Planned |
|
Achieved |
| Improve range and
pasture by:
- identification of suitable fodder and forage species for
introduction to different agro-ecological zones;
- establishment of grasses, legumes and browse species in
communal areas of the project settlement;
- introduction of improved grasses and legumes into the fallow
sequence of crop rotation;
- improvement of the species composition in rotationally
grazed enclosures used in controlled grazing schemes;
- establishment of a capacity for the production of seed
for forage and fodder species; and
- reintroduction of the traditional communal construction
of firebreaks.
Rehabilitate forestry and rangeland by encouraging
farmers and farming communities to plant trees and shrubs in
community-owned woodlots around homesteads and on farm and field
boundaries. Initial forestry efforts were to be concentrated
in the water yards/settlements where it was planned that extension
would operate. The Forestry Department was to be responsible
for establishing a small nursery at each settlement or water
yard community.
Establish drought-tolerant species of browse shrubs,
trees and grasses in areas generally not subject to heavy grazing
or where local communities have agreed to restrict and control
grazing. |
|
The range and pasture
improvement programme succeeded in establishing a capacity for
forage seed production. It also identified a number of potential
forage strategies, including community managed enclosures, fallow
improvement and fodder banks, together with suitable forage
species. However, much time was lost; testing was limited to
very few sites; and adoption was still embryonic by the end
of the project.
No information is available on the rehabilitation
of forestry and rangeland.
The establishment of drought-tolerant species
was only attempted during the first two years of the project. |
Animal health
| Planned |
|
Achieved
|
| Improve the capacity
of the veterinary services to effectively control major epidemic
diseases through provision of a drug revolving fund. |
|
With project support,
the veterinary services maintained their vaccination coverage
on an animal population that increased by 50% during project
implementation. The level of immunization against the main cattle
diseases (Rinderpest and CBPP) increased from 55-60% to 70%
over the same period, apparently due to an improved outreach
programme. The project also built and equipped a diagnostic
laboratory and installed a vaccine production capacity that
started operations in 1993/94. By the end of the project, there
were 15 private practices involved in selling drugs and services.
|
Lessons learned
A complex project needs clear objectives, an explicit strategy and
close supervision in the early stages. In any integrated area development
project, too many components, implementing agencies and financiers
may hinder coordination and focus. - Careful planning of water development, rather than settlements,
was probably the most feasible strategy to improve land use at the
regional level. However, it should have been recognized that this
environmental objective was not compatible with full cost recovery,
which scared people back to the over-populated areas where water was
freely available. Moreover, an area project was not the right instrument
to address problems of a national scope, such as the reform of water
policies and institutions.
- Expatriate staff without local senior counterparts were entrusted
with many project implementation tasks, creating a risk that there
would be no senior Sudanese staff to continue activities at the end
of the project. In such circumstances, housing and training incentives
may be necessary to attract suitably qualified national staff. A professionally
organized recruitment of staff, uniform terms and conditions of employment,
and clearly defined responsibilities help to minimize friction among
employees.
- Project performance is dependent upon the efficiency and service
capability of the cooperating institutions. Therefore, the effectiveness
and coordination of their management and information flow is crucial
to project success.
- Extensive research to identify any area's rangeland management needs,
constraints and possibilities is advisable before range improvement
activities begin.
|
| Project information |
Total
project cost: USD 43.6 million, Livestock cost (as percentage of total):
23%
Beneficiaries: The beneficiaries comprised the rural population of South
Darfur (approximately 50 000 households or 350 000 individuals).
The average per capita income of the project area population was estimated
at USD 56, far below the national average of USD 400.
Project area: The project area encompassed the entire province of South Darfur with
its estimated population of 1.18 million (1983 Census), including about
200 000 nomads. The cattle population of the area was estimated at
about 3 million head.
|
| References |
Report and Recommendation of the President to the Executive
Board.
Appraisal Report.
Project Completion Report.
Evaluation Summary. |
|
|