Evaluation Oct 2004

  • Introduction
  • Changes
  • Evaluation of project
  • lessons learned
  • Design Considerations
  • Strategic Framework
  • Components
  • Implementation
  • Potential Risks
  • Achievements
  •  

    Project

  • Project description
  • Strategic framework
  • Investment components
  • Key documents
  •  

    Informations

  • Acronym and abbreviation
  • Maps
  • Pictures
  • Archive (previous news)
  • The team
  • Download
  •  

     

     

    Achievments (results) phase I based on trigger indicators as of May 2004

    Achievement (Results)  Based on Trigger Indicators

    CAPACITY BUILDING COMPONENT

    Domestic Water Supply

    INDICATOR

    UNITY

    PLANNED

    ACHIEVEMENT

    RATE

    COMMENT

    The feasibility study of gravity piped scheme has been completed

    Study

    1

    0

     

    Water Master Plan has been completed, but has not been operationalized

    If the outcome is positive, the detailed engineering of the scheme has been done, contracts awarded, and construction well underway

    Constructed Unit

         

    Tendering process for detailed engineering study of  water schemes is planned in October, 2003

    The survey of present situation of Boreholes in the Umutara has been done, and decision taken about the number and location of Boreholes to be drilled and roof catchment houses to equip

    Number

    200

    35

    17.5%

    35 Boreholes constructed under emergency programme, otherwise Borehole programme  and Roof catchment awaits operationalization of Water Master Plan

    Rehabilitation and Repair of existing Boreholes

    Number

    67

    6

    8.9%

    Tendering process have been completed, and the bid won by Drillcon, it remains to signing contract

    All required Water Committees have been established for the piped water supply

    Number

         

    Water Committees for existing piped water supply are being reactivated and establishing new ones, where they do not exist

    Water Committees for Boreholes established 

    Number

    200

    100

    50%

    Only the water committees for Bugaragara and Gabiro districts have been formed and trained

    Water User Associations for Boreholes established at Sector level

    Number

    200

    18

    9%

    These are Water User Association for Bugaragara and Gabiro Districts only

    Hand pump money paid for 100% of the planned Boreholes

    Fund

    1 5 750 000

    2 255 430

    14.3%

    UCRIDP recruited 56 CFs for water component to assist in mobilisation activities, that would facilitate recovering the fund

    Drilling Contracts have been awarded and at least 200 successful Boreholes have been equipped

    Number

    200

    35

    17.5%

    35 Boreholes drilled  under emergency programme, and equipped with hand pumps. The new Boreholes awaits operationalization of Water Master Plan

    All Water Committees for Boreholes have been trained in pump management and repair

    Number

    200

    100

    50%

    The water committees members for UCRIDP1 have been  trained

    A commercial system to distribute hand pumps spare parts has been started

    system

         

    Modality of operation is under study

    The contract with NGO responsible for the Roof catchment  programme has been awarded, the necessary artisans trained in at least 1000 houses equipped

    Houses

    1000

    0

     

    The NGO responsible for Roof catchment has not been recruited yet, and training of artisans have not been started

     