UCRIDP-PDRCIU

Umutara Community Resource and infrastructure development project

contact site map print  

Français

Home> Interphase Evaluation - Achievements - page 1 2 3 4 5 6 7

 

Evaluation Oct 2004

  • Introduction
  • Changes
  • Evaluation of project
  • lessons learned
  • Design Considerations
  • Strategic Framework
  • Components
  • Implementation
  • Potential Risks
  • Achievements
  •  

    Project

  • Project description
  • Strategic framework
  • Investment components
  • Key documents
  •  

    Informations

  • Acronym and abbreviation
  • Maps
  • Pictures
  • Archive (previous news)
  • The team
  • Download
  •  

     

     

    Achievments (results) phase I based on trigger indicators as of May 2004

    Achievement (Results)  Based on Trigger Indicators

    CAPACITY BUILDING COMPONENT

    Cattle Water Points

    INDICATOR

    UNITY

    PLANNED

    ACHIEVEMENT

    RATE

    COMMENT

    The Umutara Cattle Water Point Master Plan has been prepared

    Unit

    1

    1

     

    Final discussion and approval of Water Master Plan will take place early October, 2003

    Rehabilitation and construction of Valley dams

    Number

         

    9 Valley dams have been rehabilitated, and the  evaluation report for the bid of constructing 4 new dams and  rehabilitation of 12 dams completed

    At least half of the CWPUA have been established and trained

    Number

     

    9

     

    Only 9 CWPUAs have been established, but not yet trained. Training is planned in October, 2003

    Existing Valley dams have been turned over to CWPUAs

    Number

    33

    0

     

    9 Rehabilitated valley dams are managed by CWPUAs, and training in management is planned in October,2003

    Feeder Roads

    The entire Feeder  construction programme has been planned and contracts awarded for construction

    km

    300

       

    Feeder roads Master plan has been prepared with community participation, it was commissioned by consultative councils, sector councils, and approved by District and Province Task Forces

    At least 200 km have been commissioned

    Km

    200

    13.7

    6.8%

    Rehabilitation of 13.7 km, on HIMO and as pilot project, has been completed

             

    Evaluation of bidders for rehabilitation of 97.5Km &for detailed study of 151Km completed by NTB

     

     

     