Home> Interphase Evaluation - Achievements - page 1 2 3 4 5 6 7

 

Evaluation Oct 2004

  • Introduction
  • Changes
  • Evaluation of project
  • lessons learned
  • Design Considerations
  • Strategic Framework
  • Components
  • Implementation
  • Potential Risks
  • Achievements
  •  

    Project

  • Project description
  • Strategic framework
  • Investment components
  • Key documents
  •  

    Informations

  • Acronym and abbreviation
  • Maps
  • Pictures
  • Archive (previous news)
  • The team
  • Download
  •  

     

     

    Achievments (results) phase I based on trigger indicators as of May 2004

    Achievement (Results)  Based on Trigger Indicators

    ORGANISATION AND MANAGEMENT ARRANGEMENTS COMPONENT

    INDICATOR

    UNITY

    PLANNED

    ACHIEVEMENT

    RATE

    COMMENT

    The project Coordination Unit (PCU) and the Steering Committees are established

    Unit

    2

    2

    100%

     

    The project Personnel recruited and Functioning

    Number

    24

    40

    166.6%

    Increment of staff due to bad design of the project

    The project Implementation Manual has been drafted and approved

    Number

    1

    1

    100%

    The PIM has been revised, but has not yet been approved

    The construction of the PCU office and houses are completed, furnished and equipped

    Unit

    4

    0

     

    The architectural design have been completed and Tendering process underway

    All project Vehicles have been procured

    Number

    15

    15

    100%

    10 Vehicles for Mayors, and 2 additional vehicles for service providers have been bided

    All Motorcycles for service providers have been procured

    Number

    21

    21

    100%

    Additional 31 Motorcycles for service providers have been bided

    All Bicycles for Service Providers have been procured

    Number

    47

    213

    453.2%

    The higher rate derives from bicycles donated to sector coordinators and Presidents of CDCs, who initially were not planned

    Service agreements with Public agents have been successfully negotiated for all project components, performance is satisfactory

    Contracts

    5

    5

    100%

     

    Performance Evaluation of Public agents conducted

    Number

    1

    1

    100%

    Notwithstanding all difficulties encountered by the service providers, but the performance has been rated satisfactorily

    All service agreements with the International NGOs have been negotiated, NGOs performance is satisfactorily

    Number

    5

    5

    100%

     

    Performance Evaluation of I-NGOs conducted

    Number

    1

    1

    100%

    The reports have not yet been approved by PCU

    At least one Annual Participatory Sub component Performance evaluation workshop have been held for all components

    Number

    3

    1

    100%

    The project organised only one Participatory Component performance evaluation workshop due to shortage of staff

     

     

     