UCRIDP-PDRCIU

Umutara Community Resource and infrastructure development project

contact site map print  

Français

Home> Interphase Evaluation - Evaluation - page 1 2 3 4 5 6

 

Evaluation Oct 2004

  • Introduction
  • Changes
  • Evaluation of project
  • lessons learned
  • Design Considerations
  • Strategic Framework
  • Components
  • Implementation
  • Potential Risks
  • Achievements
  •  

    Project

  • Project description
  • Strategic framework
  • Investment components
  • Key documents
  •  

    Informations

  • Acronym and abbreviation
  • Maps
  • Pictures
  • Archive (previous news)
  • The team
  • Download
  •  

     

     

    Evaluation of Project Performance and Impact

    Component-by-Component Evaluation

    The assessment that follows provides insights into the design and performance of the project’s components and sub-components. More detailed analyses are contained in the individual working papers.

    Capacity Building – Community Development.  A major effort was made under this component to develop a participatory planning process in the districts, to train the decentralized structures including the Community Development Committees at district, sector and cell levels (some over 500 in total), and to create a body of facilitators (about 100) that enabled the project to carry out the participatory planning referred to above. In addition, the staff responsible for the implementation of the sub-component worked together with the other project components to develop the community support and ownership structures to help ensure the operation and maintenance of rural infrastructure, particularly water points, and the formation of enterprise groups and primary savings groups (GRFs). They have also provided PRA training to government staff in the districts and province and in organizations such as ISAR.

    One of the important outputs of this process was the preparation of district development plans that represent the expressed needs and priorities of the communities and provide the base for implementation of the other project components.  While the different groups have been formed and trained, the project has been less successful in delivering the specified funding to them. The picture is similar with other elements. For example, for the construction of district and sector offices. Only one of the six district offices planned under the component was constructed and none of the 73 sector offices (40 in the first project and 33 in the twin) has been constructed. The change in the requirement for district offices explains the first and while there have been no sector offices constructed by UCRIDP, the 20 offices are to be built by the Common Development Fund (CDF) and tenders have been prepared for construction of some 60 offices by the programme. There are also questions about the functionality of the water user groups formed around the boreholes constructed by the project during the first phase (35 borehole water committees and 7 dam water user associations). This indicates that there could have been better linkages between the service providers constructing the water facilities and those responsible for training the committees/associations.

    Capacity Building – Women in Development.  This sub-component has also been one of the more successful ones in achieving its objectives. Most of the targets were either achieved or in some cases exceeded. Implementation focused on:  gender training and recruitment of gender staff in the districts (target 4, trained and in place 8 gender officers); formation and training of women’s groups at cell level (target 60; 352 formed); gender training of members of representative organizational structures at district, sector and cell levels (target and achieved 2 600); an NGO-implemented functional literacy programme (target 2 500 women; 3 455 trained); and while not formally part of this sub-component, the same team successfully formed women’s community savings groups (an initiative linked to the Group Revolving Funds). Similar to the previous experience, the one physical asset planned in this sub-component – district women’s centres – have not as yet been constructed.

    Rural Infrastructure – Water Supply.  Construction of domestic and cattle water infrastructure was the most important project activity – as per the projected investment – during the first phase, with a USD 12 million budgeted. However, less then USD 1 million was spent. Among the reasons for the minimal level of disbursement were the delays in finalizing the water master plan, sometimes weak support from the responsible I-NGOs and delays in preparation of studies – for example, 60 studies of new piped water schemes were planned during the first phase but none were completed. But, now that a water master plan for the Province has been finished (mid-2003), there is a sound basis to do the detailed planning for future implementation of water infrastructure. The assessment of the sub-component indicates that management and organization have been major constraining factors in the poor performance. As noted in Working Paper 2, Water Investment Programme, there has been:  inadequate planning of the water activities; poor communication between the various partners (project, district staff, contracted NGO, etc.); insufficient involvement of the local authorities to support the work of the NGOs in the process of mobilisation of the communities; insufficient decentralization of the water management; and insufficient capacity of PCU to handle all the tasks related to management of the water programme. For the limited number of facilities established during this phase (the 35 emergency boreholes sunk in 2001), there have been additional constraints, including:  lack of capacity to repair the pumps at village level and availability of spare parts for the installed pumps, neither in Umutara nor in Kigali. But, it should be noted that during the past quarter, the PCU has commissioned studies that will facilitate the installation of facilities in early 2004.

    Rural Infrastructure – Feeder Road Programme.  With the aim of providing road access within 5 km of all communities (a somewhat strange basis for such a dispersed rural population), project design provided for construction/rehabilitation of 477 km (300 km in the first project districts and 177 km in the twin project districts) over the project life, with 85% or over 400 km planned to be constructed/rehabilitated during the first phase. At the time of the evaluation mission, only one road of 14 km had been constructed but studies had been completed for the construction/rehabilitation of another 40 km of roads. It should be noted that the quality of the work on the completed road has not been adequate and the road is already eroding. In addition to the problem of construction, there is a question of the arrangements for maintenance of the road. Road maintenance teams (cell) and brigades (sector) have not been formed and trained nor has the necessary equipment and tools been made available. A detailed analysis of the roads programme and the performance of the team in implementing it are contained in Working Paper 3, Feeder Road Programme. The Paper highlights five key constraints that have negatively impacted on the implementation of the programme:  (i) the preparation of a roads master plan for 300 km was very delayed; (ii) for most of the period, there had been an absence of qualified staff to handle the programme (e.g. there is no roads or civil engineer in the PCU); (iii) the involvement and mobilization of the communities in the rehabilitation and subsequently the maintenance of the roads had not been clearly defined; (iv) the tendering process and approvals from the National Tender Board have been very long; and (v) the estimated cost per km of the roads FRw 4.5 million) was unrealistically low and was not revised.

     

     
    © 2005 - Terms of use

    top