UCRIDP-PDRCIU

Umutara Community Resource and infrastructure development project

contact site map print  

Français

Home> Interphase Evaluation - Evaluation - page 1 2 3 4 5 6

 

Evaluation Oct 2004

  • Introduction
  • Changes
  • Evaluation of project
  • lessons learned
  • Design Considerations
  • Strategic Framework
  • Components
  • Implementation
  • Potential Risks
  • Achievements
  •  

    Project

  • Project description
  • Strategic framework
  • Investment components
  • Key documents
  •  

    Informations

  • Acronym and abbreviation
  • Maps
  • Pictures
  • Archive (previous news)
  • The team
  • Download
  •  

     

     

    Evaluation of Project Performance and Impact

    Component-by-Component Evaluation

    On-Farm Development Support – Technology Advisory Services.  The design of the sub-component sees a substantial portion of the investment allocated to ISAR (and an international research organization that works with it):  close two thirds of the total funding for the sub-component. The majority of these funds are for staff salaries, vehicles, motorcycles and equipment for the research station. While this would not necessarily be a problem, with the M&E system still not fully operational and its ability to assess project impact limited, it is difficult to see what the impact of these expenditures have been on the farmers and how ISAR’s activities are linked to and respond to farmers’ priorities for support. The other area for concern is that there is no strategy or design of the On-Farm Development Support component in the appraisal report and no detailed specification of the implementation arrangements for the component, nor of this sub-component. The only information contained in the appraisal working papers (of the twin project) is a proposal for research support. It has thus been difficult for the evaluation team to assess whether the sub-component has performed well or not. The project’s internal evaluation report indicates that some 40 farmers were involved in technology tests but that only six farmers adopted new technology (out of a planned 280) and that there were only 10 ‘innovator farmers’ (out of a planned 24). In contrast, progress was achieved in participatory diagnosis of production farmers’ problems (30 out of 47 sectors planned) and a study on carrying capacity was completed. Nevertheless, what is clear is that there needs to be considerable effort made to develop a practical strategy for both this sub-component and the component as a whole that demonstrates clearly how farmers and other rural households participate in the programme and benefit from its implementation. Working Paper 4 attempts to describe how such technical advisory services could be implemented but the Programme management team will need to carry this work forward into detailed monitorable work programmes.

    On-Farm Development Support – Agricultural Production.  This sub-component responds to one of the most critical constraints for farmers in the province:  poor seed quality. It is rather support for improved seed production and distribution than of the broad-based agricultural production that the title implies. The design of this programme has been a problem, as indicated by the minimal achievements attained. While a reported 130 seed multipliers were identified, trained and contracted, the amount of seed produced was only enough for sale to the project with none being sold to the communities. The programme also included provision for the construction of four seed multiplication and fertilizer distribution centres; however, none were constructed. Seven sites have been identified for construction of such centres in the second phase, but there are still outstanding questions about how these centres will be managed and whether they will become public or private assets.

    A second programme included under this sub-component is:  seed and fertilizer distribution to vulnerable households. This was planned to be a substantial programme with 12 000 households to receive a package of seeds (only 7 400 households received packs), seedlings and inputs, as a grant. While these households are definitely among the poorer households in the province, the logic of providing production inputs free needs to be reassessed. The packages have not always been used effectively and training in use of the package should be a prerequisite in any future programme.

    On-Farm Development Support – Veterinary and Livestock Production.  The limited budget and attention to the design of this programme in the appraisal belie the importance that livestock has in the province – it is the major livestock production area of the country. A wide range of activities were identified, but no detailed design was done and the activities lack implementation strategies. Furthermore, the sub-component was under-budgeted. The programme includes the following activities:  (i) delivery of veterinary services by selected community members through the funding of a ‘community animal health agents (‘paravets’)’ scheme; (ii) reinforcing the capacity of the districts’ veterinary technicians to carry out participative diagnostic of livestock’s owners constraints, (iii) establishment of a stock of veterinary drugs and vaccines, (iv) experiments and trials on the production and improvement of fodder crops and improvement of rangelands, (v) promotion of animal traction through demonstrations, (vi) support the improvement of local breed through the introduction of quality genitor of improved breed, (vii) construction of four pilot livestock markets; and (viii) exploration of improved livestock production technologies/practices.  Relatively few of these initiatives were implemented and those that were started with a considerable delay. The paravet scheme, for example, did not start till the third year but with the contracting of an international NGO ‘Veterinary without Border’, the programme was successful in developing a training manual and selecting and training some 40 community animal health agents and providing them with starter kits. The project also co-financed a vaccination campaign against CBPP, trained of task force members and established 12 on-farm trials and demonstration of fodder crops. The formulation of the appraisal report nor the working papers related to livestock did not provide the implementation and phasing of such activities. Considerably more attention and budget needs to be allocated to livestock development in the second phase with particular attention given to commercialisation, the forming of livestock owners associations and the support for the milk commodity chain.

    On-Farm Development Support – Forestry.  The implementation of this sub-component was one of the more successful and the performance of the international NGO charged with its implementation was good. The objective was to respond to the increasing demand for wood products while addressing the problem of environmental degradation caused by the indiscriminate cutting of forests for building materials for new settlers and opening of new grazing and cropping lands. The target was to establish 2400 ha of district forests and woodlots and fruit tree plantations for vulnerable households. To achieve this, it was planned to establish individual 40 nurseries; due to a very attractive price of seedlings (twice the going price), 164 nurseries were established that produced sufficient seedlings to plant 1227 ha of forests and 32.5 ha of fruit trees, reflecting an achievement rate of 102% and 81% respectively.. This good performance it provides valuable experience for implementing a second phase forest management programme.

    Rural Financial Services.  The major focus of the component during the first phase the formation of Group Revolving Funds (GRFs) and women’s investment funds (WIDs). The project was extremely successful in forming both types of bodies with some 169 GRFs and 654 women groups formed in five of the eight districts, which indicates the strong need for such institutions. But, they operate primarily as community savings associations, some based on the traditional tontines with rotational withdrawal of savings by one of the members and others taking in savings and providing loans to the members. However, in both cases, the sums are small and very often the uses of the funds are social rather than economic. They provide an important facility for rural households and are also one of the few initiatives that have allowed women to develop their own savings and in some cases get access to credit. Two issues arise:  firstly, the new Central Bank legislation would appear to make these institutions illegal unless they can meet the registration requirements (which for most is extremely unlikely) and secondly, the practice of providing grants to the WIFs is now recognized as inappropriate and goes counter to sound financial management and sustainability and they need to be translated into credit. This initiative formed part of the first sub-component for rural finance: development of microfinance institutions. The implementation of the rest of the component has been considerably delayed, due to a number of constraints, including:  (i) difficulties in agreeing on an appropriate modus operandi for implementation of rural finance between the project and IFAD, which delayed the recruitment of microfinance institutions (MFIs) to provide support to the project, including technical assistance to GRFs and other solidarity groups; (ii) lack of staff in the PCU (one single person in charge of capacity-building and financial services components); and more recently, (iii) difficulties in defining an implementation strategy compatible with the Central Bank instruction on microfinance and with methodologies currently applied in the microfinance sector in Rwanda. There has been no provision of funds to the groups (as promised as part of the project support) and no provision of training in accounting and financial management. However, the project has recently contracted two MFIs – Duterimbere and CSC Ugama – on a trial basis for a few months, each responsible for pilot programmes in two districts. They have yet to start operations. The strong interest in savings and credit groups and the possibility of developing new approaches to the provision of financial service through the two MFIs should be used as a basis to create a new financial services programme in the second phase.

    Project Management Support.  This investment component provides for the salaries of the PCU plus the associated vehicles, equipment and some civil works (offices and two houses). The original staffing proposed for the PCU was dramatically underestimated, even for only four districts, with only three professional staff provided for (project coordinator, financial controller and project evaluation officer). Even with the addition of the twin project the staffing was only increased by two (deputy project coordinator and community development officer). Project management is discussed further in the following paragraphs.

     
    © 2005 - Terms of use

    top