UCRIDP-PDRCIU

Umutara Community Resource and infrastructure development project

contact site map print  

Français

Home> Interphase Evaluation - Evaluation - page 1 2 3 4 5 6

 

Evaluation Oct 2004

  • Introduction
  • Changes
  • Evaluation of project
  • lessons learned
  • Design Considerations
  • Strategic Framework
  • Components
  • Implementation
  • Potential Risks
  • Achievements
  •  

    Project

  • Project description
  • Strategic framework
  • Investment components
  • Key documents
  •  

    Informations

  • Acronym and abbreviation
  • Maps
  • Pictures
  • Archive (previous news)
  • The team
  • Download
  •  

     

     

    Evaluation of Project Performance and Impact

    Project Coordination and Institutional Aspects

    PCU.  The performance of the PCU in guiding/facilitating project implementation and providing project oversight has been less than ideal. This is due to a number of factors:

    · Inadequate staffing and often insufficiently experienced staff.  As noted, the original budget for staffing the PCU was totally inadequate. While this was recognized early in project implementation and action was taken to strengthen the unit, it was done in a piecemeal fashion and to-date the PCU is still lacking in capacity to effectively manage the project. The frequent changes in project coordinators did not help – three in as many years – and in some cases the shortage of sufficiently skilled and experienced staff in the PCU has also handicapped its operations. While the numbers have been progressively increased – the PCU now numbers eight – there are still problems in achieving effective and timely management of resources in spite of a high level of commitment and hard work of the current staff.

    · Time-consuming processing.  The time required to handle even very simple administrative and financial matters can be excessive. This is recognized by all parties, including the staff of the PCU. While staff shortages and experience have been contributing factors, there are other problems that need to be addressed:  contract management procedures and processes are slow, bureaucratic; and review/approval/no objection processes (by the Tender Board and UNOPS) are lengthy as sometimes is the submission of AWPBs by project partners.

    Oversight/Coordination Structures.  The design of the project’s two-tier oversight structure involving national and provincial steering committees needs to be re-examined. It was observed in the review of the project’s performance over the first phase – as presented in the internal evaluation report – that the provincial steering committee was too large to be a fully effective mechanism to support the PCU and that a smaller committee or working group should be considered. A question was also raised as to whether both national and provincial steering committees were needed for a project whose operations were fully contained within one province.

    Implementation Arrangements.  The basic arrangements for project implementation, as presented in the appraisal reports, are effective and have allowed the project to execute its range of investment programmes. However, two aspects need specific comment:  (i) the project’s contractual arrangements with NGOs and (ii) the role of districts in the project’s development process. As mentioned previously, the performance of NGOs has been negatively affected by the current management arrangements. The proposed role of the I-NGOs as both funding and contracted parties for the project has not been ideal and has caused tensions among the partners. Further, the expected transfer of knowledge and experience from I-NGOs to N-NGOs has been less than ideal and the I-NGO consortium while providing a useful forum for exchange of information among the members has not brought the advantages originally foreseen. Working relations have not been helped by the fact that the international NGOs have been operating without contracts and from their own resources for most of 2003. While there are a number of reasons for this – including delays in and questions arising from performance evaluations – and questions as to what extent the I-NGOs have actually had to use their own resources, there has been nevertheless a difficult working relation between many of the I-NGOs and the project.

    To implement the various project activities has required that the project develop close working relations with the districts – something that it has done diligently and well. The districts have been partners in the planning of project activities and in their implementation. But, to-date it has been the project that has been making the decisions and the districts that have been responding. The project identifies the needs (together with the districts), identifies suitable service providers, draws up contracts with the ones that successfully respond to the project’s request for proposals and oversees the performance of the contracts. The district is the recipient and the project the deliverer. The nation’s decentralization policy sees the district becoming the ‘decision maker’ and consequently being accountable. To achieve this will require a major change in ‘mind set’ in the project and a consequent reorientation of project management procedures and resources.

    Financial Management

    Disbursements and Use of Funds.  Firstly, to-date (end-October 2003) only 13.6% of project funds for Phase I have been disbursed with the highest disbursement rate being for the following expenditure categories:  salaries (87%), operating costs (68%) and vehicles and equipment (68%). This contrasts with the minimal disbursement in civil work (2%), financial services (0%) and revolving funds (0%). In terms of use of funds by component, the current percentages of funds disbursed are:  community development (12%), infrastructure (10%), on-farm investment (18%), rural financial services (0%) and project coordination (34%).

    Annual Work Programme and Budgets (AWPBs).  Review of the process of preparing/approving AWPBs indicates that while the project has been preparing and using AWPBs, the draft budgets (for government and IFAD/UNOPS approval) have been submitted several months late (contravening Section 3.03 of the Loan Agreement).

    Contract Management.  As noted above, contract management is an area in which the PCU requires considerable strengthening. It has been observed that:  (i) there is a difference in understanding regarding the detailing of tasks in the NGO contracts, with the project claiming they are sufficiently detailed and the NGOs claiming they are not, which does not facilitate the annual task of performance evaluation; (ii) a one year ‘Protocole d’Accord Cadre’ (framework agreement) was signed with the consortium of I-NGOs in April 2001 that, in understanding of the I-NGOs, was in principle renewable annually, however, it has never been formally renewed; (iii) annual contracts with each service provider vary in terms and conditions (e.g. advances range from 30% to 70% with no apparent reason) and in the degree to which they specific obligations of the contractee and its reporting commitments; and (iv) the contracts entered into with public institutions such as ISAR and the Department of Agriculture, Livestock and Forestry (DALF) have no legal basis (as they are between a government project and government agencies. The most important observation is that considerably more effort must be put into preparing contracts to ensure that the service providers understand their tasks and obligations and that the PCU (and progressively the districts) are able to effectively monitor their performance. This requires much closer working relationships between the financial controller and the technical staff of the PCU to ensure that the technical requirements are well specified in the body of the request for proposals and subsequently in the contracts that are awarded.

    Procurement.  The analysis of the procurement process has been constrained by an inadequate documentation and filing system in the PCU, however, it is evident that the time required to procure services has been long:  on average seven months. The delays are due to slow processing in all three major steps in the procurement system:  request and evaluation of bids, approval by the National Tender Board and issuance of ‘no-objection’ by UNOPS.

    Accounting System and Internal Control.  The general organization of the accounting is satisfactory although the PCU has not as yet fully converted to the TOMPRO software. The internal control system currently used by the PCU while effective is too lengthy and should be simplified without altering the quality of the control. It has also been observed that the project is too centralized in its organization and operations; there is considerable scope for a responsible delegation of power within the PCU to facilitate processing efficiency. Plus the processing of performance based contracts and their evaluation was too heavy to be implemented properly by a small PCU.

    In summary, it can be stated that the PCU has struggled with the financial management of the project. Due to overly centralized decision making and cumbersome and lengthy processing procedures compounded by lack of relevant project administration experience of some key staff and understaffing problems, there have been accumulating delays. This has had serious repercussions on the project’s delivery of services and investment, as is evidenced by the low disbursement rate up to October 2003.

     
    © 2005 - Terms of use

    top