Pabna Irrigation and Rural Development Project - IFAD
- Who we are
Transparency and Accountability Ethics Anticorruption Evaluation Social, Environmental and Climate Assessment Procedures Corporate Procurement Operations Dashboard
- What we do
- Where we work
- Action Areas
Protecting the environment Climate and environment BiodiversityEnhancing livelihoods and markets Private sector Rural finance Markets and value chains Managing land and its resourcesBuilding resilience Rural institutions & organizations Remittances Nutrition Fragile contexts and crises
- Knowledge & Data
- Get Involved
- Who we are
- About IFAD
- Our People
- Governance
- Transparency and Accountability
- What we do
- Investing in Rural People
- How We Work
- Our Impact
- Where we work
- Action Areas
- Empowering rural people
- Protecting the environment
- Enhancing livelihoods and markets
- Promoting sustainable farming
- Building resilience
- Knowledge & Data
- Get Involved
- News and Stories
Project
Pabna Irrigation and Rural Development Project
Country
Bangladesh
Sector
Irrigation
Approval Date
11 December 1978
Duration
1978 - 1992
Project ID
1100000009
Pabna Irrigation and Rural Development Project
This, IFAD's first project in Bangladesh, was created to improve the basic infrastructure of one of the most important and vulnerable agricultural areas in the heart of the country. It was designed to increase agricultural production, generate employment and improve farmers' living conditions by providing flood embankments, improving existing channels and installing drainage pumps to protect an area of about 185,000 ha from annual flooding.
Source: IFAD
Additional Data
-
Total Project Cost
US$ 85 million
-
IFAD Financing
US$ 30 million
-
Financing terms
Highly Concessional
Co-financiers (International)
-
Asian Development Bank
US$ 38 million
Co-financiers (Domestic)
-
National Government
US$ 17 million