Second National Agricultural Extension Project - IFAD
Welcome Popup disabled (visible only in edit mode)
Second National Agricultural Extension Project
The long period of restructuring of IFAD’s investments in Kenya that began with the country portfolio review in 1995 led to a year-long disbursement suspension. Working in collaboration with the Government, IFAD closed ongoing projects at their stipulated closing dates. In addition, the Government requested the anticipated closing of one non-performing project, the Western Kenya District based Agricultural Development Project.
Total cost: US$45.84 million
IFAD loan amount: US$9.37 million
Duration: 1996-1998
Type: research, extension and training
Additional Data
-
Total Project Cost
US$ 37.22 million
-
IFAD Financing
US$ 0.75 million
-
Financing terms
Highly Concessional
Co-financiers (International)
-
World Bank: International Development Association
US$ 24.9 million
Co-financiers (Domestic)
-
National Government
US$ 11.57 million